Pembangunan Waduk Rawa Badung Capai 90 Persen

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Indonesia-Singapore Match: 80 Dishub Personnel Deployed to Manage Traffic Around GBK

    access_time25-09-2026 remove_red_eye637 personAldi Geri Lumban Tobing
  2. Jakarta International Stadium Sets Up Transit Schemes for The Weeknd Concert

    access_time24-09-2026 remove_red_eye495 personAldi Geri Lumban Tobing
  3. Jakarta Calls on Residents to Save Energy with 60-Minute Lights-Off Action

    access_time19-09-2026 remove_red_eye436 personAldi Geri Lumban Tobing
  4. South Jakarta BPBD Distributes 44,000 Liters of Clean Water

    access_time19-09-2026 remove_red_eye372 personTiyo Surya Sakti
  5. Jakarta Inspectorate Partners with KPK to Foster Early Anti-Corruption Culture

    access_time20-09-2026 remove_red_eye322 personFolmer