You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Waduk Rawa Badung Capai 90 Persen

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1300 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1131 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye840 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye296 personAldi Geri Lumban Tobing
  5. Travelers Departing from Lebak Bulus Terminal Starting to Increase

    access_time13-03-2026 remove_red_eye286 personTiyo Surya Sakti