Rawa Badung Reservoir Project Almost Complete
access_time December 12 2015 08:13 PM remove_red_eye 2176
Reported by Nurito | Translated by Trias Risangayu
Reported by Nurito | Translated by Trias Risangayu
The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.
The plastering work has been run for 200 meters out of 300 meters
Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.
“The plastering work has been run for 200 meters out of 300 meters,” he said.
Damaged Sheet Pile in Pulo River in Jati Padang RepairedMeanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.
It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.