You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan Waduk Rawa Badung Capai 90 Persen
.
photo Nurito - Beritajakarta.id

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1223 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1058 personAldi Geri Lumban Tobing
  3. First Jakarta Update Talks Nataru up to Water Tariff Adjustment

    access_time24-12-2024 remove_red_eye1051 personDessy Suciati
  4. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye913 personAldi Geri Lumban Tobing
  5. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye737 personFolmer