Pembangunan Waduk Rawa Badung Capai 90 Persen
.
photo Nurito - Beritajakarta.id

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. MSMEs Bazaar Held at Binus Anggrek Campus

    access_time30-10-2024 remove_red_eye968 personTP Moan Simanjuntak
  2. 250 High School Students in N. Jakarta Learn to Create Digital Content

    access_time01-11-2024 remove_red_eye783 personBudhi Firmansyah Surapati
  3. W. Jakarta SDA Constructs Channel on Jalan Nurul Muslimin I Kembangan

    access_time04-11-2024 remove_red_eye738 personTP Moan Simanjuntak
  4. 18 School Principals Participate in Public Agency E-Monev Presentation

    access_time02-11-2024 remove_red_eye451 personFolmer
  5. South Jakarta City Government Accelerates Stop BABS

    access_time31-10-2024 remove_red_eye414 personTiyo Surya Sakti