Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Kampung Melayu Sports Facility Inaugurated to Tackle Brawls

    access_time06-11-2026 remove_red_eye435 personDessy Suciati
  2. Commission D Calls for Integrated Air Quality Monitoring System

    access_time06-11-2026 remove_red_eye415 personFakhrizal Fakhri
  3. Aid for Fire Survivors at Pinus Elok Flats Has Been Distributed

    access_time06-11-2026 remove_red_eye409 personNurito
  4. House Fire in Sunter Agung Successfully Extinguished

    access_time04-11-2026 remove_red_eye406 personAnita Karyati
  5. Faith Meets Progress, Ancol Prayer Gathering Fortifies Jakarta’s Journey as a Global City

    access_time01-11-2026 remove_red_eye406 personAnita Karyati