Pembangunan Waduk Rawa Badung Capai 90 Persen
.
photo Nurito - Beritajakarta.id

Rawa Badung Reservoir Project Almost Complete

The construction of Rawa Badung Reservoir in Jatinegara Urban Village, Caking, East Jakarta, has reached 90 percent. The 4 meters dredging work has been done and awaits for plastering.

The plastering work has been run for 200 meters out of 300 meters

Ahmad Yazied, East Jakarta Head Sub-dept. of Water Management, targeted to finish the Rp 9.9 billion reservoir project by the middle of this month.

“The plastering work has been run for 200 meters out of 300 meters,” he said.

Damaged Sheet Pile in Pulo River in Jati Padang Repaired

Meanwhile, the jogging track construction and plants planting will be done by Sub-dept. of Cemeteries and Park.

It is hoped that the 1.8 ha reservoir will be able to accommodate 3,000 cubics water to anticipate flood around the area.

Linked News
Popular News indeks
  1. Takjil Supervision in Central Jakarta Begins Second Week

    access_time02-03-2025 remove_red_eye457 personBudhi Firmansyah Surapati
  2. Government Declares Ramadhan Starts on March 1, 2025

    access_time28-02-2025 remove_red_eye418 personBudhi Firmansyah Surapati
  3. Dishub: Lay Bay Remains Optimal to Support Public Transportation User Comfort

    access_time02-03-2025 remove_red_eye385 personAldi Geri Lumban Tobing
  4. Orderly Sidewalk Operation Targets Many Streets in Jakarta

    access_time27-02-2025 remove_red_eye376 personAldi Geri Lumban Tobing
  5. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye341 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik