You don't have javascript enabled. Good luck with that.
Pencarian
 Jalan Layang Semanggi Selesai Agustus 2017

Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. Jakarta Government Guarantees Full Medical Care for Bantargebang Landslide Victims

    access_time09-03-2026 remove_red_eye1300 personDessy Suciati
  2. Commission E Supports Restricting Children's Access to Social Media

    access_time09-03-2026 remove_red_eye1131 personFakhrizal Fakhri
  3. Affordable and High-Quality Staple Goods Offered at Ramadan Bazaar

    access_time09-03-2026 remove_red_eye840 personAldi Geri Lumban Tobing
  4. Jakarta Planetarium Rolls Out Varied Shows for Eid al-Fitr Holiday

    access_time11-03-2026 remove_red_eye296 personAldi Geri Lumban Tobing
  5. Travelers Departing from Lebak Bulus Terminal Starting to Increase

    access_time13-03-2026 remove_red_eye285 personTiyo Surya Sakti