 Jalan Layang Semanggi Selesai Agustus 2017

Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1591 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1443 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1307 personFolmer
  4. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye968 personDessy Suciati
  5. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye948 personDessy Suciati