 Jalan Layang Semanggi Selesai Agustus 2017
.
photo Reza Hapiz - Beritajakarta.id

Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. Pramono Prioritizes Construction of Cakung Regional Hospital

    access_time18-04-2025 remove_red_eye473 personFakhrizal Fakhri
  2. Governor Pramono Joins Cycling in Jakarta Silaturahride 2025

    access_time19-04-2025 remove_red_eye413 personBudhi Firmansyah Surapati
  3. Jakarta to Make Public Transportation Free on April 24, 2025

    access_time18-04-2025 remove_red_eye325 personAldi Geri Lumban Tobing
  4. City Goverment Encourages Residents to Use Public Transportation

    access_time21-04-2025 remove_red_eye286 personFakhrizal Fakhri
  5. Transjakarta Applies Special Fares for Female Customers

    access_time20-04-2025 remove_red_eye278 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik