 Jalan Layang Semanggi Selesai Agustus 2017
.
photo Reza Hapiz - Beritajakarta.id

Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye465 personFolmer
  2. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye357 personFolmer
  3. Food Station Signs Farming Contracts in Rorotan

    access_time12-05-2025 remove_red_eye291 personAldi Geri Lumban Tobing
  4. Commission D Supports Construction of Rorotan Rusunawa

    access_time10-05-2025 remove_red_eye257 personFakhrizal Fakhri
  5. Pramono Focuses on Increasing Equal Access to Education

    access_time15-05-2025 remove_red_eye241 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik