Semanggi Elevated Road to Finish in August 2017

Jakarta Dept. of Bina Marga targets to finish Semanggi elevated road construction in 18 months. The construction is started on Friday (4/8) and to complete in August 2017. It is hoped the elevated road would able to decrease traffic jam.

Our target is completed in August 2017

Yusmada Faizal, Jakarta Head Dept. of Bina Marga, explained the project takes 540 calendar days including 60 days of planning and 480 days of construction.

“Our target is completed in August 2017,” he said, Friday (4/8).

Semanggi Interchange Project Begins

The elevated road projects are detail engineering design (DED), preparation, loop shifting, construction implementation, and drainage as well as traffic sign.

Two elevated road will be built. First is from Grogol to Blok M direction by 796 meters and Polda to Monas direction by 826 meters.

Linked News
Popular News indeks
  1. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye1184 personFakhrizal Fakhri
  2. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye996 personAldi Geri Lumban Tobing
  3. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye953 personAldi Geri Lumban Tobing
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye731 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye631 personAnita Karyati