Multifunction Space and New Entrance Construction at Bundaran HI Station Reaches 33.95 Percent

The construction progress of the multi-function space (extended concourse) and new entrance at Bundaran HI Bank Jakarta Station has shown satisfactory results since it began in February 2026. As of October 2026, construction had reached 33.95 percent, or exceeded the target of 31.61 percent.

Interconnection with commercial areas

A number of major works such as excavation and installation of struts and wallers at estuaries 1 and 2, mechanical, electrical, and plumbing intakes, wall work, as well as heating, ventilation, and air conditioning (HVAC) work are continuing.

MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

Corporate Secretary Division Head of PT MRT Jakarta, Rendy Primartantyo, said that the construction of this new multifunctional space and entrance is part of preparations for the potential increase in the number of customers during the upcoming phase 2A operations.

"This addition is also part of the development of underground circulation and opens up the potential for interconnection with commercial areas," he said, Monday (11/16).

He added that a space of approximately 4,400 square meters will be presented to be used as a retail, F&B, service, and partnership area according to customer needs.

This extended concourse area will feature 24 multi-function areas that will be filled by a number of tenants, as well as providing activation space for holding various public activities and events.

The plan calls for the construction of a multi-function space and the addition of three new entrances namely two on the west side of the station and one on the east side. Two of the entrances will be equipped with stairs and escalators, while one will have an elevator leading to the pedestrian areas on the left and right sides of Jalan M.H. Thamrin.

"This area will be accessible via the elevator at the Bundaran HI Astra Transjakarta bus stop. In addition to the multifunctional space and new entrance, a cooling and ventilation tower will also be built," he added.

Rendy explained that completion is targeted for mid-2027. This development also aims to make the Bundaran HI Bank Jakarta Station a transit-oriented area center that promotes interconnection with surrounding buildings, in accordance with the transit-oriented development principles adopted by PT MRT Jakarta.

As for information, the Bundaran HI Bank Jakarta station, which is 18 meters below ground level, is one of the busiest stations on Phase 1 of the North-South Line, with an average of 450,000 to 500,000 customers per month. This number is predicted to continue to increase once Phase 2A of the North-South Line, Segment 1, Bundaran HI-Monas, begins operation.

"The construction of this new multifunctional space and center is in preparation for the operational phase 2A segment 1 to Monas which is targeted for the end of 2027 and to the city at the end of 2029," he stated.

Linked News
Popular News indeks
  1. Jakarta Removes Gibran’s Portraits Across All Government Offices

    access_time16-11-2026 remove_red_eye1045 personFakhrizal Fakhri
  2. Transjakarta Offers Free Rides for Jakarta Vertical Run 2026 Participants

    access_time14-11-2026 remove_red_eye671 personAldi Geri Lumban Tobing
  3. Governor Approves Removal of Seven Unauthorized Houses on Dispora Land

    access_time13-11-2026 remove_red_eye649 personFakhrizal Fakhri
  4. Pramono Outlines Measures to Address Five Issues in Kramat Jati

    access_time13-11-2026 remove_red_eye629 personFakhrizal Fakhri
  5. Jakarta Esports 2026 Draws Enthusiastic Crowds at M Bloc Space

    access_time13-11-2026 remove_red_eye606 personTiyo Surya Sakti