Six Plots of Land in Rambutan 1 Dam Not Yet Acquired
Reported by Nurito | Translated by Nugroho Adibrata
Although its construction has been started, six plots of land in Rambutan 1 Dam, East Jakarta is not yet acquired. As planned, the land acquisition would be executed by the end of this month.
Next month, we'll acquire two plots on the north. Each has between 500-2,950 square meters wide
Section Staff of River and East Flow Beach for Jakarta Water Management Dept, Asep Setia Permana disclosed, in project location, there are three points that consist of six plots have not been acquired.
He mentions, each point is located on the west side or at RW 04 with three plots that have 300 meters wide. Other points are on the south side or at RT 03/06 with one plot.
Rambutan 1 Dam Project Accelerated"Next month, we'll acquire two plots on the north. Each has between 500-2,950 square meters wide," he expressed (8/5).
He explains two plots on the north of Rambutan 1 Dam is still under measurement process by National Land Agency (BPN). After that, it will be continued to administration and verification process. "Talk about price, there has been agreement," he disclosed.
He is optimistic such project could be complete within three months in line with land acquisition.