Pembangunan Waduk Rambutan Terkendala Pasokan BBM Alat Berat

Rambutan Reservoir Construction Reaches 15 Percent

The construction of Rambutan Reservoir 1 at RW 04 and 06, Rambutan Urban Village, Ciracas Sub-district, East Jakarta is being accelerated. Hundreds of building have been demolished.

Reservoir construction is still running

The project by five hectare of land is targeted to complete this year.

East Flow River and Beach System Staff for Jakarta Dept. of Water Management, Asep Setia Permana, said the project has reached 15 percent. His side will remain dig the land since it has been bought.

City Uses Reservoir to Handle Water Crisis

“Reservoir construction is still running,” he said.

His side is still providing Detail Engineering Design (DBD) for the reservoir, as well as the existing dike. Reservoir will has depth about 3.5 meters and surrounded by dike as wide as three meters.

Meanwhile, East Jakarta Mayor, Bambang Musyawardana, hoped the construction can be accelerated faster. The reservoir will overcome puddle caused by Cipinang river overflows.

“The reservoir must be completed as soon as possible. It will decrease Cipinang river water debit,” he stated.

Linked News
Popular News indeks
  1. BMKG: Sunny to Cloudy Skies Forecast Across Jakarta Today

    access_time11-09-2026 remove_red_eye1703 personDessy Suciati
  2. Jakarta Reallocates Funds for Rp 250M Suckermouth Catfish Study After Pramono’s Direct Order

    access_time10-09-2026 remove_red_eye699 personFakhrizal Fakhri
  3. Pramono Urges Jakmania to Keep Jakarta Safe

    access_time11-09-2026 remove_red_eye456 personDessy Suciati
  4. Pramono Endorses Five-City Tour for Jazz Goes to Campus

    access_time12-09-2026 remove_red_eye436 personDessy Suciati
  5. No Damage Reported Following Magnitude 5.9 Seribu Islands Quake

    access_time12-09-2026 remove_red_eye420 personBudhi Firmansyah Surapati