Pemasangan SGB Simpang Susun Semanggi Sudah 87 Persen

Semanggi Intersection SGB Installation Reaches 87 Percent

Segmental Gear Box (SGB) installation in Semanggi Intersection recently has reached 87 percent from total of 395 SGB that will be installed in ramp 1 and ramp 2.

SGB installation for ramp 1 already finished since mid March

City Bina Marga Dept. Intersection and Overpass Division Head, Heru Suwondo admitted he is optimistic this SGB installation can be finished in the mid April.

"SGB installation for ramp 1 is already finished since mid March. SGB installation has reached 87 percent," he said, Monday (3/27).

December, 14 At-Grade Intersections in Jakarta Closed

After SGB installation process is done, the next step is finishing process in other parts such as asphalting, lamps and road signs installment.

"All progress done is about 67 percent," he closed.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2633 personNurito
  2. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2354 personTiyo Surya Sakti
  3. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye975 personFolmer
  4. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye836 personFakhrizal Fakhri
  5. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye734 personBudhi Firmansyah Surapati