Pemasangan SGB Simpang Susun Semanggi Sudah 87 Persen
.
photo istimewa - Beritajakarta.id

Semanggi Intersection SGB Installation Reaches 87 Percent

Segmental Gear Box (SGB) installation in Semanggi Intersection recently has reached 87 percent from total of 395 SGB that will be installed in ramp 1 and ramp 2.

SGB installation for ramp 1 already finished since mid March

City Bina Marga Dept. Intersection and Overpass Division Head, Heru Suwondo admitted he is optimistic this SGB installation can be finished in the mid April.

"SGB installation for ramp 1 is already finished since mid March. SGB installation has reached 87 percent," he said, Monday (3/27).

December, 14 At-Grade Intersections in Jakarta Closed

After SGB installation process is done, the next step is finishing process in other parts such as asphalting, lamps and road signs installment.

"All progress done is about 67 percent," he closed.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye397 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye352 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye324 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye316 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik