Semanggi Intersection SGB Installation Reaches 87 Percent

Segmental Gear Box (SGB) installation in Semanggi Intersection recently has reached 87 percent from total of 395 SGB that will be installed in ramp 1 and ramp 2.

SGB installation for ramp 1 already finished since mid March

City Bina Marga Dept. Intersection and Overpass Division Head, Heru Suwondo admitted he is optimistic this SGB installation can be finished in the mid April.

"SGB installation for ramp 1 is already finished since mid March. SGB installation has reached 87 percent," he said, Monday (3/27).

December, 14 At-Grade Intersections in Jakarta Closed

After SGB installation process is done, the next step is finishing process in other parts such as asphalting, lamps and road signs installment.

"All progress done is about 67 percent," he closed.

Linked News
Popular News indeks
  1. Traffic Diverted on Jalan Jatinegara Barat as Floods Hit Jakarta

    access_time04-03-2025 remove_red_eye382 personNurito
  2. Rano Supports Schools to Organize Study Tours to Museums

    access_time08-03-2025 remove_red_eye313 personBudhi Firmansyah Surapati
  3. TMII Launches Jelajah Cerita Ramadan Program with Umroh Grand Prize

    access_time08-03-2025 remove_red_eye307 personNurito
  4. North Jakarta PPKD Provides Training for Students with Disabilities

    access_time07-03-2025 remove_red_eye306 personAnita Karyati
  5. BPPOM Finds Harmful Substances in Ramadhan Takjil Snacks in Rawamangun Market

    access_time07-03-2025 remove_red_eye304 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik