Pemasangan SGB Simpang Susun Semanggi Sudah 87 Persen

Semanggi Intersection SGB Installation Reaches 87 Percent

Segmental Gear Box (SGB) installation in Semanggi Intersection recently has reached 87 percent from total of 395 SGB that will be installed in ramp 1 and ramp 2.

SGB installation for ramp 1 already finished since mid March

City Bina Marga Dept. Intersection and Overpass Division Head, Heru Suwondo admitted he is optimistic this SGB installation can be finished in the mid April.

"SGB installation for ramp 1 is already finished since mid March. SGB installation has reached 87 percent," he said, Monday (3/27).

December, 14 At-Grade Intersections in Jakarta Closed

After SGB installation process is done, the next step is finishing process in other parts such as asphalting, lamps and road signs installment.

"All progress done is about 67 percent," he closed.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1092 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye575 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye500 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye480 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye476 personBudhi Firmansyah Surapati