Pemasangan SGB Simpang Susun Semanggi Sudah 87 Persen

Semanggi Intersection SGB Installation Reaches 87 Percent

Segmental Gear Box (SGB) installation in Semanggi Intersection recently has reached 87 percent from total of 395 SGB that will be installed in ramp 1 and ramp 2.

SGB installation for ramp 1 already finished since mid March

City Bina Marga Dept. Intersection and Overpass Division Head, Heru Suwondo admitted he is optimistic this SGB installation can be finished in the mid April.

"SGB installation for ramp 1 is already finished since mid March. SGB installation has reached 87 percent," he said, Monday (3/27).

December, 14 At-Grade Intersections in Jakarta Closed

After SGB installation process is done, the next step is finishing process in other parts such as asphalting, lamps and road signs installment.

"All progress done is about 67 percent," he closed.

Linked News
Popular News indeks
  1. Suckermouth Catfish Control for Environmental Preservation

    access_time18-04-2026 remove_red_eye786 personFakhrizal Fakhri
  2. Suckerfish Handling in South Jakarta is Run in Accordance with MUI Recommendations

    access_time21-04-2026 remove_red_eye622 personTiyo Surya Sakti
  3. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye481 personAldi Geri Lumban Tobing
  4. Jakarta Newcomers Mostly in Productive Age

    access_time22-04-2026 remove_red_eye383 personAldi Geri Lumban Tobing
  5. East Jakarta Steps Up Services to Simplify Population Registration

    access_time20-04-2026 remove_red_eye356 personNurito