Pemasangan 295 SBG Simpang Susun Semanggi Rampung
.
photo istimewa - Beritajakarta.id

Semanggi Intersection Construction Reaches 75 Percent

As many as 295 units of segmental box girder (SBG) in two ramps of Semanggi intersection have been installed. Currently, construction progress reaches 75 percent.

We will also restore the condition of parks and roads which affected by the construction

Jakarta Bina Marga Dept. Head, Yusmada Faizal said, after SBG installation, his side will complete the other parts such as on off ramp, parapet (barrier), hot mix coating, traffic sign, and lighting for bridge.

"We will also restore the condition of parks and roads affected by the construction," he said, Wednesday (4/26).

July, Open Traffic at Semanggi Interchange Trialled

Related to bridge's lighting, he explained that its operation will be integrated with smart city system. Thus colors and patterns setting can be controlled depends on the theme through smart city system.

"We have two months to work it. According to plan, we will open traffic trial in July," he closed.

Linked News
Popular News indeks
  1. Mothers Attack Cheap Market in Cibubur Urban Village

    access_time02-05-2024 remove_red_eye574 personNurito
  2. LRT Phase 1B Construction Remains Positive

    access_time27-04-2024 remove_red_eye460 personAldi Geri Lumban Tobing
  3. S. Jakarta Residents Enjoy NIK Deactivation Consultation Post Services in Rawajati

    access_time30-04-2024 remove_red_eye358 personTiyo Surya Sakti
  4. Sunny All Day Long in Jakarta

    access_time03-05-2024 remove_red_eye323 personAnita Karyati
  5. Secretariat General Bureau-Information Commission Holds E-Monev Bimtek 2024

    access_time28-04-2024 remove_red_eye292 personAnita Karyati