Perbaikan Tanggul di Pulau Untung Jawa Sudah 42 Persen
.
photo Suparni - Beritajakarta.id

Dike Repair in Untung Jawa Island Reaches 42 Percent

Dike repair in east side of Untung Jawa Island, Seribu Islands, reaches 42 percent. Currently, along 126 meters has been repaired from total 300 meters to be repaired.

This dike will be connected to Sakura Beach

Seribu Islands Water Resources Sub-dept. Head, Mustajab said, dike repair is using cube-shape old material which is re-arranged and cemented thus can be stronger.

"This dike will be connected to Sakura Beach," he said, Tuesday (5/9).

Type A Sea Dike Able to Minimize Flood, Basuki Says

He explained more than 3,000 old cubes were collected since January. It has been collected from the seashore, middle of the sea, or around the damaged breakwater.

"This dike is not only functioned as abrasion holder, but also could be used as ring road because it is constructed surround the island," he closed.

Linked News
Popular News indeks
  1. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye334 personNurito
  2. City - DBL Committed to Develop Basketball and Youth Development

    access_time03-05-2025 remove_red_eye304 personBudhi Firmansyah Surapati
  3. Kampung Bayam Madani Farmer Group Harvests 138 Kilograms of Agriculture and Fishery Commodities

    access_time05-05-2025 remove_red_eye271 personAnita Karyati
  4. Uus Releases 39 Prospective Hajj Pilgrims in Semanan

    access_time03-05-2025 remove_red_eye269 personFolmer
  5. Jakarta Projected to Become a Sports Tourism Destination

    access_time04-05-2025 remove_red_eye269 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik