This Year, Sea Dike Pole Targeted to Be Installed in April 2018

It is targeted to be complete in 2018. The fastest finishing us maybe in 2017

The pile installation as long as 2.2 kilometers for sea dike in Kalibaru and Cilincing areas, North Jakarta is targeted to be complete in the upcoming April 2018.

April 2018, Kalibaru-Cilincing Sea Dike Completed

Until December 2016, the project is targeted can be constructed up to 400 meters long.

"It is targeted to be complete in 2018. The fastest finishing us maybe in 2017," said Teuku Iskandar, Head of Ciliwung-Cisadane Flood Control Office (BBWSCC), Tuesday (9/13).

He disclosed it is still constrained in the company's activities that do any cutting of scrap metal not far from the location.

"We ask for the cooperation of employers thus construction could run smoothly," he expressed.

According to him, sea dike trace that built will cross a portion of the company's land. Even, the spun pile installation is predicted to approach the company's land in November 2016.

"We hope related unit can follow up any obstacles," he closed.

Linked News
Popular News indeks
  1. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1039 personNurito
  2. Jakarta KPU Records More Than 8.2 Million Registered Voters

    access_time06-07-2026 remove_red_eye967 personFolmer
  3. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye918 personDessy Suciati
  4. MRT Phase 2A Northbound Tunnel Excavation Completed

    access_time09-07-2026 remove_red_eye747 personAldi Geri Lumban Tobing
  5. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye732 personFolmer