This Year, Sea Dike Pole Targeted to Be Installed in April 2018

It is targeted to be complete in 2018. The fastest finishing us maybe in 2017

The pile installation as long as 2.2 kilometers for sea dike in Kalibaru and Cilincing areas, North Jakarta is targeted to be complete in the upcoming April 2018.

April 2018, Kalibaru-Cilincing Sea Dike Completed

Until December 2016, the project is targeted can be constructed up to 400 meters long.

"It is targeted to be complete in 2018. The fastest finishing us maybe in 2017," said Teuku Iskandar, Head of Ciliwung-Cisadane Flood Control Office (BBWSCC), Tuesday (9/13).

He disclosed it is still constrained in the company's activities that do any cutting of scrap metal not far from the location.

"We ask for the cooperation of employers thus construction could run smoothly," he expressed.

According to him, sea dike trace that built will cross a portion of the company's land. Even, the spun pile installation is predicted to approach the company's land in November 2016.

"We hope related unit can follow up any obstacles," he closed.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye899 personAldi Geri Lumban Tobing
  2. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye601 personAldi Geri Lumban Tobing
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye578 personDessy Suciati
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye568 personFakhrizal Fakhri
  5. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye431 personNurito