Pembangunan Tanggul Laut Terhalang Kegiatan Pemotongan Besi Kapal Tua

This Year, Sea Dike Pole Targeted to Be Installed in April 2018

It is targeted to be complete in 2018. The fastest finishing us maybe in 2017

The pile installation as long as 2.2 kilometers for sea dike in Kalibaru and Cilincing areas, North Jakarta is targeted to be complete in the upcoming April 2018.

April 2018, Kalibaru-Cilincing Sea Dike Completed

Until December 2016, the project is targeted can be constructed up to 400 meters long.

"It is targeted to be complete in 2018. The fastest finishing us maybe in 2017," said Teuku Iskandar, Head of Ciliwung-Cisadane Flood Control Office (BBWSCC), Tuesday (9/13).

He disclosed it is still constrained in the company's activities that do any cutting of scrap metal not far from the location.

"We ask for the cooperation of employers thus construction could run smoothly," he expressed.

According to him, sea dike trace that built will cross a portion of the company's land. Even, the spun pile installation is predicted to approach the company's land in November 2016.

"We hope related unit can follow up any obstacles," he closed.

Linked News
Popular News indeks
  1. Attending Betawi Eid 2026, Pram Encourages Strengthening Cultural Values

    access_time11-04-2026 remove_red_eye1106 personFolmer
  2. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye1058 personAldi Geri Lumban Tobing
  3. Pademangan Health Center Promotes 3M Plus to Prevent Dengue Fever

    access_time14-04-2026 remove_red_eye772 personAnita Karyati
  4. Jakarta Provincial Government Fully Supports BTN JAKIM 2026

    access_time14-04-2026 remove_red_eye687 personDessy Suciati
  5. Transjakarta Adjusts Route 6D Tebet Station-Bundaran Senayan

    access_time14-04-2026 remove_red_eye517 personAldi Geri Lumban Tobing