Pembangunan Simpang Susun Semanggi Masuk Tahap Finishing

Semanggi Interchanges Project Has Entered Finishing

The Semanggi Interchanges construction has entered finishing stage. Until now, it has reached 94 percent.

It's approximately less than six percent more to be completed

According to Heru Suwondo, Head of Overpass and Intersection Division at Jakarta's Bina Marga Agency, the current project only leaves minor work such as lighting improvement, marking painting, partial installation and reinstatement.

"There is also asphalting on ramp position. It's approximately less than six percent more to be completed," he disclosed, Monday (7/17).

15 Box Girders in Ramp 1 of Semanggi Interchanges Installed

He explains, on July 29, his side will hold a soft launching about intersection prior to inauguration on August 17.

"We open traffic, meaning the vehicle may pass. And on August 17, we will do the inauguration," he stated.

Linked News
Popular News indeks
  1. Pramono Affirms Commitment to Enhancing Regional Financial Management Quality

    access_time02-04-2026 remove_red_eye791 personTiyo Surya Sakti
  2. Pramono Calls for Enhanced Synergy at DPRD Post-Eid Gathering

    access_time30-03-2026 remove_red_eye698 personDessy Suciati
  3. Banners Prohibiting Illegal Parking Levies Installed at Blok M Square

    access_time02-04-2026 remove_red_eye638 personTiyo Surya Sakti
  4. Kampung Rambutan Terminal Sees Increase in Intercity Bus Passengers

    access_time03-04-2026 remove_red_eye566 personNurito
  5. Gov Pramono: Jakarta Prepared to Adopt Weekly WFH Scheme

    access_time30-03-2026 remove_red_eye446 personDessy Suciati