Pembangunan Simpang Susun Semanggi Masuk Tahap Finishing
.
photo istimewa - Beritajakarta.id

Semanggi Interchanges Project Has Entered Finishing

The Semanggi Interchanges construction has entered finishing stage. Until now, it has reached 94 percent.

It's approximately less than six percent more to be completed

According to Heru Suwondo, Head of Overpass and Intersection Division at Jakarta's Bina Marga Agency, the current project only leaves minor work such as lighting improvement, marking painting, partial installation and reinstatement.

"There is also asphalting on ramp position. It's approximately less than six percent more to be completed," he disclosed, Monday (7/17).

15 Box Girders in Ramp 1 of Semanggi Interchanges Installed

He explains, on July 29, his side will hold a soft launching about intersection prior to inauguration on August 17.

"We open traffic, meaning the vehicle may pass. And on August 17, we will do the inauguration," he stated.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye396 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye352 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye324 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye316 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik