You don't have javascript enabled. Good luck with that.
Pencarian
Pembangunan RPTRA Johar Baru Capai 42 Persen

Johar Baru Construction Has Touched 42 Percent

The stage of drying or construction strengthening is very important. Hence the process can take place 10 days

The construction of Johar Baru RPTRA, Central Jakarta has reached 42.91 percent. It is targeted to be completed in the upcoming October.

"The stage of drying or construction strengthening is very important. Hence the process can take place 10 days," expressed Muhammad Fahmi, Assistant for Central Jakarta People's Welfare, Tuesday (9/19).

RPTRA Construction Progress in Cengkareng Has Reached 50 Percent

According to him, if it is not completed optimally, it will not last long and quickly collapse. "If it's not maximal, the building can collapse," he expressed.

Meanwhile, Johar Baru Urban Village Head added RPTRA with 500 square meters width would have a jogging track. Thus local people can use to exercise.

"If there is no obstacle, it will be inaugurated on October 10," he stated.

Linked News
Popular News indeks
  1. Nighttime Surveillance on Railroad Banks of Jalan I Gusti Ngurah Rai Intensified

    access_time08-05-2026 remove_red_eye2620 personNurito
  2. Governor Pram Appreciates Residents for Keeping Jakarta Safe and Comfortable

    access_time09-05-2026 remove_red_eye959 personFolmer
  3. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye814 personFakhrizal Fakhri
  4. Fire Burns Five Houses in Cengkareng Extinguished

    access_time12-05-2026 remove_red_eye720 personBudhi Firmansyah Surapati
  5. Jakarta`s 499th Anniversary and a Waste Sorting Movement Launched

    access_time10-05-2026 remove_red_eye696 personTiyo Surya Sakti