Johar Baru Construction Has Touched 42 Percent

The stage of drying or construction strengthening is very important. Hence the process can take place 10 days

The construction of Johar Baru RPTRA, Central Jakarta has reached 42.91 percent. It is targeted to be completed in the upcoming October.

"The stage of drying or construction strengthening is very important. Hence the process can take place 10 days," expressed Muhammad Fahmi, Assistant for Central Jakarta People's Welfare, Tuesday (9/19).

RPTRA Construction Progress in Cengkareng Has Reached 50 Percent

According to him, if it is not completed optimally, it will not last long and quickly collapse. "If it's not maximal, the building can collapse," he expressed.

Meanwhile, Johar Baru Urban Village Head added RPTRA with 500 square meters width would have a jogging track. Thus local people can use to exercise.

"If there is no obstacle, it will be inaugurated on October 10," he stated.

Linked News
Popular News indeks
  1. Jakarta Council Begins Deliberations on New Population and Housing Bylaws

    access_time21-08-2026 remove_red_eye1804 personFakhrizal Fakhri
  2. Jakarta Assesses Needs and Coordinates Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye734 personAldi Geri Lumban Tobing
  3. Jakarta Prepares Aid for NTT Earthquake Victims

    access_time16-08-2026 remove_red_eye684 personDessy Suciati
  4. Pramono: Independence must Be Manifested Through Concrete Action

    access_time17-08-2026 remove_red_eye684 personDessy Suciati
  5. Pramono Commends Madurese Community for Their Vital Role in Building Jakarta

    access_time19-08-2026 remove_red_eye656 personDessy Suciati