Penataan Trotoar di Tanjung Priok Capai 60 Persen
.
photo Nurito - Beritajakarta.id

Sidewalk Project in Tanjung Priok Has Touched 60 Percent

Total length of the sidewalk is about 1.6 kilometers by spending Rp 7 billion

The arrangement and development of the sidewalks in Tanjung Priok area, North Jakarta has reached 60 percent. It is targeted to be completed in early December 2017.

Section Head of Road Infrastructure and Utility Network Completeness, Libertus Sagala stated the sidewalk arrangement on Jalan Enggano has 1.3 kilometers length and 300 meters length on Jalan Yos Sudarso. Both are interconnected with each other. 

Sidewalk Arrangement on Jl. Sudirman-MH Thamrin Launched

"Sidewalk arrangement in Tanjung Priok Sub-district has reached 60 percent. Total length of the sidewalk is about 1.6 kilometers by spending Rp 7 billion," he stated, Monday (10/9).

It will be equipped with the guiding block and the utility block. Additionally, there will be bollards along the sidewalk. Then for its surface will use floor hardener.

He added those utility installation will use drilling method through ducting box that is installed with a distance every 25 meters. Box ducting itself has 2.5 meters depth with 2 meters length.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye554 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye488 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye421 personAldi Geri Lumban Tobing
  4. City Submits 2024 Financial Report to BPK

    access_time26-03-2025 remove_red_eye356 personBudhi Firmansyah Surapati
  5. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye310 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik