Pembangunan Velodrome Rawamangun Sudah 62,29 Persen

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. Jakarta Announces Rp 1 Fare for Transjakarta, MRT, and LRT on August 17

    access_time13-08-2026 remove_red_eye898 personAldi Geri Lumban Tobing
  2. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye601 personAldi Geri Lumban Tobing
  3. Pramono Urges MUI to Strengthen Synergy in Maintaining Jakarta’s Harmony

    access_time12-08-2026 remove_red_eye577 personDessy Suciati
  4. Jakarta Ensures Public Services Stay Operational After Abdul Muis Building Fire

    access_time08-08-2026 remove_red_eye566 personFakhrizal Fakhri
  5. Fire Site in Utan Kayu Utara Being Cleared

    access_time11-08-2026 remove_red_eye430 personNurito