photo istimewa - Beritajakarta.id

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. Free Additional Nutritious Food Distributed to 31 Toddlers in Kalibata

    access_time13-09-2024 remove_red_eye1146 personTiyo Surya Sakti
  2. Jakarta Women's Football Team Ready to Face West Java at PON XXI Final

    access_time13-09-2024 remove_red_eye845 personFolmer
  3. Water Channel Dredging on Bendungan Melayu Reaches 50 Percent

    access_time18-09-2024 remove_red_eye825 personAnita Karyati
  4. Jakarta Leads Medal Standing at PON XXI

    access_time17-09-2024 remove_red_eye775 personFolmer
  5. PON XXI Temporary Standings: Jakarta Continues to Shadow East Java

    access_time13-09-2024 remove_red_eye754 personAldi Geri Lumban Tobing