Pembangunan Velodrome Rawamangun Sudah 62,29 Persen

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. Closure of Railway Level Crossings Socialized

    access_time13-05-2026 remove_red_eye2427 personTiyo Surya Sakti
  2. Telkomsel Digiland Run 2026 Parking Lot List: Check Now!

    access_time14-05-2026 remove_red_eye1154 personAldi Geri Lumban Tobing
  3. Governor Pramono Named Vice Chair of C40 Cities Steering Committee

    access_time18-05-2026 remove_red_eye968 personAldi Geri Lumban Tobing
  4. Pramono: Jakarta Remains the Capital City Until a Presidential Decree Is Issued

    access_time13-05-2026 remove_red_eye934 personDessy Suciati
  5. Waste Sorting Movement Boosts Circular Economy

    access_time12-05-2026 remove_red_eye907 personFakhrizal Fakhri