Pembangunan Velodrome Rawamangun Sudah 62,29 Persen
.
photo istimewa - Beritajakarta.id

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. Commission D Legislator Supports Park Monitoring Optimization

    access_time20-01-2025 remove_red_eye1505 personDessy Suciati
  2. Realizing Food Self-Sufficiency, Jakarta Holds Simultaneous Planting Activity

    access_time21-01-2025 remove_red_eye927 personAldi Geri Lumban Tobing
  3. Gulkarmat to Intensify Fire Mitigation Education

    access_time22-01-2025 remove_red_eye397 personBudhi Firmansyah Surapati
  4. City and Kejati Forge Cooperation for Good Government Governance

    access_time21-01-2025 remove_red_eye393 personFolmer
  5. BMKG Warns of Potential High Rainfall in Jakarta

    access_time22-01-2025 remove_red_eye392 personDessy Suciati