Pembangunan Velodrome Rawamangun Sudah 62,29 Persen

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. 129 Motorcycle Parked Illegally in Daan Mogot Controlled

    access_time08-11-2026 remove_red_eye754 personBudhi Firmansyah Surapati
  2. BPBD Prepares 403 Evacuation Sites to Mitigate Floods in Jakarta

    access_time08-11-2026 remove_red_eye523 personBudhi Firmansyah Surapati
  3. Pramono Launches JEKATE Running 2026, Promotes Healthy Living

    access_time08-11-2026 remove_red_eye505 personDessy Suciati
  4. BI and Jakarta Government Deepen Investment, Creative Economy Collaboration

    access_time09-11-2026 remove_red_eye504 personAldi Geri Lumban Tobing
  5. Tourism and Creative Economy Boost Jakarta's Economic Growth

    access_time08-11-2026 remove_red_eye467 personDessy Suciati