Pembangunan Velodrome Rawamangun Sudah 62,29 Persen

June 2018, Velodrome Rawamangun Finished

Construction of one of the Asian Games XVIII venues, Velodrome Rawamangun, East Jakarta, has reached 62.29 percent on the cut off date August 29, 2017.

It's targeted to be completed in June 2018

PT Jakarta Propertindo (Jakpro) Secretary, Erry Gunari Prakasa expressed the achievement has exceeded the set target at 61.90 percent.

"The Velodrome Rawamangun bike racing venue is built on a 3-hectare wide land. It's targeted to be completed in June 2018," he state, Tuesday (10/17).

5 Stations will Be on Velodrome-Kelapa Gading LRT Lane

To absorb budget according to cut off date August 29, he explained, it has reached Rp 332.8 billion of total financing amounting to Rp 665 billion.

He added the venue is built internationally and directly monitored by Union Cycliste International (UCI) of Germany. It is equipped with amenities such as bike entrances, bike workshops, toilets with a capacity of 3,000 seats.

"On the structure and surface of the track, using Siberian wood that reaches 6,500 cubic meters," he closed.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1783 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1555 personFakhrizal Fakhri
  3. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1150 personFakhrizal Fakhri
  4. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1124 personBudhi Firmansyah Surapati
  5. Commission E Enlists Religious Leaders to Fight Drugs and Violence

    access_time24-07-2026 remove_red_eye1071 personFakhrizal Fakhri