Pembanguan Equestrian Park Sudah 95 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Equestrian Park Project Has Touched 92 Percent

PT Pulomas Jaya Presidential Director, Bambang Mursalin, disclosed Equestrian Park construction on Jalan Pulo Mas, East Jakarta has touched 92 percent.

Equestrian park construction has entered in finishing stage

"Equestrian park construction has entered in finishing stage. Currently we're awaiting the geotextile components that we import from Germany as much as 10,000 tons of components," he explained, Monday (3/12).

He expressed the component is used for out door game area. In addition, the mixture also serves to keep the moisture and keep the density when the horse weighing 700 kilograms jump.

Pulomas Equestrian Project Has Touched 93 Percent

This component will be mixed with sand every square meter of 3-4 kilograms.

"It makes the sand becomes elastic. If the horse stepped on the sand, the sand won't form a hole but it returns to its original state," he said.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye723 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye616 personFolmer
  3. Backflow at Kampung Rambutan Terminal Increases as Mudik Return Flow Peaks

    access_time04-04-2025 remove_red_eye460 personNurito
  4. District Community Health Centers in East Jakarta Operate for 24 Hours

    access_time05-04-2025 remove_red_eye460 personNurito
  5. Kalideres Bus Terminal Adds 55 Night Transport Units

    access_time05-04-2025 remove_red_eye354 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik