Pembanguan Equestrian Park Sudah 95 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Equestrian Park Project Has Touched 92 Percent

PT Pulomas Jaya Presidential Director, Bambang Mursalin, disclosed Equestrian Park construction on Jalan Pulo Mas, East Jakarta has touched 92 percent.

Equestrian park construction has entered in finishing stage

"Equestrian park construction has entered in finishing stage. Currently we're awaiting the geotextile components that we import from Germany as much as 10,000 tons of components," he explained, Monday (3/12).

He expressed the component is used for out door game area. In addition, the mixture also serves to keep the moisture and keep the density when the horse weighing 700 kilograms jump.

Pulomas Equestrian Project Has Touched 93 Percent

This component will be mixed with sand every square meter of 3-4 kilograms.

"It makes the sand becomes elastic. If the horse stepped on the sand, the sand won't form a hole but it returns to its original state," he said.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye521 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye411 personBudhi Firmansyah Surapati
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye327 personDessy Suciati
  4. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye269 personAldi Geri Lumban Tobing
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye264 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik