photo Wuri Setyaningsih - Beritajakarta.id

Equestrian Park Project Has Touched 92 Percent

PT Pulomas Jaya Presidential Director, Bambang Mursalin, disclosed Equestrian Park construction on Jalan Pulo Mas, East Jakarta has touched 92 percent.

Equestrian park construction has entered in finishing stage

"Equestrian park construction has entered in finishing stage. Currently we're awaiting the geotextile components that we import from Germany as much as 10,000 tons of components," he explained, Monday (3/12).

He expressed the component is used for out door game area. In addition, the mixture also serves to keep the moisture and keep the density when the horse weighing 700 kilograms jump.

Pulomas Equestrian Project Has Touched 93 Percent

This component will be mixed with sand every square meter of 3-4 kilograms.

"It makes the sand becomes elastic. If the horse stepped on the sand, the sand won't form a hole but it returns to its original state," he said.

Linked News
Popular News indeks
  1. Commission E Urges Residents to Increase Role in Preventing DHF

    access_time19-12-2024 remove_red_eye1207 personDessy Suciati
  2. Transjakarta Adjusting Service as Simpang Pramuka and Rawamangun Bus Stops Closed

    access_time18-12-2024 remove_red_eye1052 personAldi Geri Lumban Tobing
  3. Transjakarta, Telkomsel to Improve Service for Customers

    access_time19-12-2024 remove_red_eye905 personAldi Geri Lumban Tobing
  4. Acting Governor Monitors Food Stock at Kramat Jati and Cipinang Markets

    access_time19-12-2024 remove_red_eye729 personFolmer
  5. Jakarta Provincial Government Holds Christmas Carol

    access_time18-12-2024 remove_red_eye577 personDessy Suciati