Pembanguan Equestrian Park Sudah 95 Persen
.
photo Wuri Setyaningsih - Beritajakarta.id

Equestrian Park Project Has Touched 92 Percent

PT Pulomas Jaya Presidential Director, Bambang Mursalin, disclosed Equestrian Park construction on Jalan Pulo Mas, East Jakarta has touched 92 percent.

Equestrian park construction has entered in finishing stage

"Equestrian park construction has entered in finishing stage. Currently we're awaiting the geotextile components that we import from Germany as much as 10,000 tons of components," he explained, Monday (3/12).

He expressed the component is used for out door game area. In addition, the mixture also serves to keep the moisture and keep the density when the horse weighing 700 kilograms jump.

Pulomas Equestrian Project Has Touched 93 Percent

This component will be mixed with sand every square meter of 3-4 kilograms.

"It makes the sand becomes elastic. If the horse stepped on the sand, the sand won't form a hole but it returns to its original state," he said.

Linked News
Popular News indeks
  1. Duren Sawit PTSP Holds Door-to-Door Servies at Pondok Kelapa TPU until Thursday

    access_time15-05-2024 remove_red_eye746 personNurito
  2. Aiming to Global City, Jakarta Prioritizes the Development of Environmentally Friendly Waste Processing

    access_time13-05-2024 remove_red_eye648 personFolmer
  3. Commission D: RDF Construction in Rorotan Has Many Benefits

    access_time13-05-2024 remove_red_eye633 personFolmer
  4. 35 Toddlers in Kedoya Selatan Received Assistance with Nutritious Additional Food

    access_time13-05-2024 remove_red_eye591 personTP Moan Simanjuntak
  5. 42,878 Tourists Swarm Monas Area

    access_time12-05-2024 remove_red_eye425 personBudhi Firmansyah Surapati