photo Wuri Setyaningsih - Beritajakarta.id

Equestrian Park Project Has Touched 92 Percent

PT Pulomas Jaya Presidential Director, Bambang Mursalin, disclosed Equestrian Park construction on Jalan Pulo Mas, East Jakarta has touched 92 percent.

Equestrian park construction has entered in finishing stage

"Equestrian park construction has entered in finishing stage. Currently we're awaiting the geotextile components that we import from Germany as much as 10,000 tons of components," he explained, Monday (3/12).

He expressed the component is used for out door game area. In addition, the mixture also serves to keep the moisture and keep the density when the horse weighing 700 kilograms jump.

Pulomas Equestrian Project Has Touched 93 Percent

This component will be mixed with sand every square meter of 3-4 kilograms.

"It makes the sand becomes elastic. If the horse stepped on the sand, the sand won't form a hole but it returns to its original state," he said.

Linked News
Popular News indeks
  1. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye560 personFolmer
  2. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye496 personDessy Suciati
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye423 personAldi Geri Lumban Tobing
  4. City Submits 2024 Financial Report to BPK

    access_time26-03-2025 remove_red_eye356 personBudhi Firmansyah Surapati
  5. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye310 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik