 Progres Pembangunan MRT Capai 92,50 Persen

MRT Construction Reaches 92.50 Percent

PT. Mass Rapid Transit (MRT) Jakarta Director, William Sabandar said, MRT construction has reached 92.50 percent. This progress consists of underground station construction for 95.83 percent and elevated station for around 89.19 percent.

Until March 28, 2018, progress of MRT Jakarta project has reached 92.50 percent

"Until March 28, 2018, progress of MRT Jakarta project has reached 92.50 percent," he informed, Thursday (3/29).

Currently his side conducts track-bed casting, elevated station track casting along 11,177 meters to 18,714 meters (59.7%), and underground track casting along 3,973 meters to 12,275 meters.

Two MRT Trains Shipped From Japan

It needs to be done because train will be arrived on April and it will be tested without passengers in December 2018.

"Next, MRT will be operated in March 2019," he stated.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1092 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye575 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye500 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye480 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye476 personBudhi Firmansyah Surapati