Pembangunan Proyek MRT capai 91,86 persen
.
photo istimewa - Beritajakarta.id

MRT Construction Reaches 91,86 Percent

PT. MRT Jakarta Director, William Sabandar mentioned, Mass Rapid Transit (MRT) construction has reached 91.86 percent.

With 91.86 percent progress, it means MRT project is still on target

That progress consists of underground station which reaches 95.76 percent and elevated station with around 87.9 percent.

"With 91.86 percent progress, it means MRT project is still on target," he stated, Tuesday (2/27).

Sandi Inspects MRT Construction Progress in A Morning Run

Currently, his side is on process to complete casting, depot and railway installation. Train will be trialed without passengers in December 2018.

"After that, MRT train will start to operate in March 2019," he conveyed.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye515 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye404 personBudhi Firmansyah Surapati
  3. City Government and Hotels Promote Betawi Culture to the Global Stage

    access_time30-05-2025 remove_red_eye384 personFakhrizal Fakhri
  4. Ragunan Zoo Bustling with Holiday Visitors

    access_time30-05-2025 remove_red_eye369 personTiyo Surya Sakti
  5. Seribu Islands Presents Red and White Cooperatives in Six Urban Villages

    access_time30-05-2025 remove_red_eye319 personAnita Karyati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik