photo istimewa - Beritajakarta.id

MRT Construction Reaches 91,86 Percent

PT. MRT Jakarta Director, William Sabandar mentioned, Mass Rapid Transit (MRT) construction has reached 91.86 percent.

With 91.86 percent progress, it means MRT project is still on target

That progress consists of underground station which reaches 95.76 percent and elevated station with around 87.9 percent.

"With 91.86 percent progress, it means MRT project is still on target," he stated, Tuesday (2/27).

Sandi Inspects MRT Construction Progress in A Morning Run

Currently, his side is on process to complete casting, depot and railway installation. Train will be trialed without passengers in December 2018.

"After that, MRT train will start to operate in March 2019," he conveyed.

Linked News
Popular News indeks
  1. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye358 personTiyo Surya Sakti
  2. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye329 personAldi Geri Lumban Tobing
  3. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye319 personAldi Geri Lumban Tobing
  4. Smoke-Free Neighborhoods Could Be a Pilot Project for the KTR Regional Regulation Implementation

    access_time18-07-2025 remove_red_eye277 personFakhrizal Fakhri
  5. Council Encourages the Increase of RPTRAs for Child Growth and Development

    access_time18-07-2025 remove_red_eye276 personFakhrizal Fakhri

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik