photo Punto Likmiardi - Beritajakarta.id

MRT Project Has Touched 93.45 Percent

In details, the underground construction has touched 94.24 percent and Lebak Bukus MRT depot has touched 90.45 percent

PT Mass Rapid Transit (MRT) President Director, William Sabandar said, up to April 25, 2018, the project of MRT Phase I (Lebak Bulus-HI Roundabout) has reached 93.45 percent.

"In details, the underground construction has touched 94.24 percent and Lebak Bukus MRT depot has touched 90.45 percent," he expressed, Friday (4/27).

Sandi Drives 13 TODs in MRT Phase I Area

His side is currently conducting maintenance, as there is entrance construction on the right and left side of the station. There is also interior construction such as track work system.

"Then for railway installation has reached 60-70 percent," he stated.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye527 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye462 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye412 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye311 personTiyo Surya Sakti
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye280 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik