Pengerjaan Proyek MRT Capai 93,45 Persen
.
photo Punto Likmiardi - Beritajakarta.id

MRT Project Has Touched 93.45 Percent

In details, the underground construction has touched 94.24 percent and Lebak Bukus MRT depot has touched 90.45 percent

PT Mass Rapid Transit (MRT) President Director, William Sabandar said, up to April 25, 2018, the project of MRT Phase I (Lebak Bulus-HI Roundabout) has reached 93.45 percent.

"In details, the underground construction has touched 94.24 percent and Lebak Bukus MRT depot has touched 90.45 percent," he expressed, Friday (4/27).

Sandi Drives 13 TODs in MRT Phase I Area

His side is currently conducting maintenance, as there is entrance construction on the right and left side of the station. There is also interior construction such as track work system.

"Then for railway installation has reached 60-70 percent," he stated.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye599 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye593 personFolmer
  3. Foul Smell Around JGC Clarified Not Coming from Rorotan RDF

    access_time28-03-2025 remove_red_eye431 personAldi Geri Lumban Tobing
  4. Residents Hope Another Free Homecoming Program Held Next Year

    access_time27-03-2025 remove_red_eye317 personDessy Suciati
  5. Odd-Even Policy in Jakarta Put on Hold for Eid Break

    access_time28-03-2025 remove_red_eye292 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik