Pembangunan Breakwater Pulau Pramuka Sudah 30 Persen

Pramuka Island Breakwater Project Has Touched 30 Percent

We have done this since July 5. And now it has touched 30 percent

The 426-meter long breakwater construction along the east coast of Pramuka Island, Panggang Island Urban Village, North Seribu Islands has reached 30 percent. It is expected to be completed by the end of this year.

Seribu Islands Water Resources Sub-dept. Head, Ahmad Saiful stated that it has been carried out since last July.

Breakwater Construction on East Side of Sebira Island is Completed

"We have done this since July 5. And now it has touched 30 percent," he stated, Monday (9/17).

To realize it, his side has spent Rp 13 billion.

"It is targeted to be finished on December 10, 2018," he said.

Linked News
Popular News indeks
  1. Jakarta to Hold Citywide Lights-Out Initiative

    access_time24-04-2026 remove_red_eye803 personAldi Geri Lumban Tobing
  2. Jakarta Residents Welcome Rp1 Public Transport Fare

    access_time24-04-2026 remove_red_eye627 personNurito
  3. Limiting Gadget Use in Schools Expected to Boost Interaction and Reading Habits

    access_time24-04-2026 remove_red_eye597 personFakhrizal Fakhri
  4. Rano Leads Parking Arrangement on Jalan R.A. Kartini, Lebak Bulus

    access_time24-04-2026 remove_red_eye578 personBudhi Firmansyah Surapati
  5. PT JIEP Targets Shenzhen Businesses with Investment Offers

    access_time24-04-2026 remove_red_eye568 personAldi Geri Lumban Tobing