Perbaikan Turap Saluran Phb Alu Alu Masuki Tahap Finishing

This Week, Alu Alu Sheet Pile Repair Completed

The repair towards the 157-meter long Alu Alu connecting channel's sheet pile in Pulogadung, East Jakarta has entered finishing stage. Repair itself takes about three months using a self-managed budget by Rp 455 million.

It is targeted to be finished this week

East Jakarta Water Resources Sub-dept. Head, Mustajab stated that it has been carried out since July. 

"It is targeted to be finished this week. To do repair, we're using river rocks yet we tie it with concrete sloop so it won't break easily," he expressed, Tuesday (9/25).

November, Sheet Pile Repair at Jalan Kelapa Cengkir Finished

It is carried out, as most of the sheet piles' age in the channel is more than 20 years and have yet to be revitalized.

Linked News
Popular News indeks
  1. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye597 personAldi Geri Lumban Tobing
  2. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye549 personAldi Geri Lumban Tobing
  3. Transjakarta Modifies Mikrotrans Routes JAK 48A, JAK 50, and JAK 79

    access_time12-10-2026 remove_red_eye529 personAldi Geri Lumban Tobing
  4. Way to Go, Kid! Transjakarta Surprises Young Local Commuter in East Jakarta

    access_time11-10-2026 remove_red_eye456 personAldi Geri Lumban Tobing
  5. Jakarta Sends Transport Personnel to Street Level to Clear Morning Rush-Hour Jams

    access_time11-10-2026 remove_red_eye367 personAldi Geri Lumban Tobing