Proses Perbaikan Saluran Penghubung Kelapa Cengkir Capai 40 Persen
.
photo Budhi Firmansyah Surapati - Beritajakarta.id

Kelapa Cengkir PHB Channel Repair Reaches 40 Percent

Repair on Kelapa Cengkir PHB channel's retaining walls in Kelapa Gading Timur Urban Village, Kelapa Gading, North Jakarta is now reached 40 percent.

Total, we repair 608 meters retaining wall.

Water Resources (SDA) Sub-dept.'s Kelapa Gading Sub-district Unit Head, Rukmana explained, retaining walls on both sides of the channel are repaired along 304 meters.

Halim Perdanakusuma Reservoir's Retaining Wall Repaired

"Total, we repair 608 meters retaining wall. Currently we have repaired 300 meters or about 40 percent," he informed, Monday (10/8).

He mentioned, previously the retaining walls were broken and tilted due to tree roots.

"Hopefully it can be finished in November," he stated.

Linked News
Popular News indeks
  1. Transjakarta Targets Planting 100,000 Mangroves

    access_time12-07-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  2. Rano Karno Celebrates City's Anniversary with Kamal Residents

    access_time12-07-2025 remove_red_eye397 personFolmer
  3. Residents Enthusiastically Enjoy the Car Free Day in Kebayoran Lama

    access_time13-07-2025 remove_red_eye353 personTiyo Surya Sakti
  4. Traffic Engineering on Jalan Otista to Begin July 20 Due to JPO Revitalization

    access_time17-07-2025 remove_red_eye325 personAldi Geri Lumban Tobing
  5. MRT Jakarta Considers Route Expansion to South Tangerang

    access_time13-07-2025 remove_red_eye317 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik