 Pembangunan MRT Jakarta Fase I Capai 97,06 Persen

Phase I MRT Development Has Reached 97.06 Percent

he three percent deficiency is still in progress at the interior and entrance

The progress on the construction of the phase I Jakarta Mass Rapid Transit (MRT) plying Lebak Bulus-HI Roundabout has reached 97.06 percent.

MRT Lebak Bulus-HI Roundabout Operational Socialization Intensified

"The three percent deficiency is still in progress at the interior and entrance," expressed William P. Sabandar, President Director of PT MRT Jakarta, Tuesday (10/30).

By so, he is optimistic that it will operate in accordance with the schedule in March 2019. Because until now the target of operations is still on time.

"In December 2018-February 2019, we will touch operation trial," he stated.

Linked News
Popular News indeks
  1. Temporary Crosswalk to Be Built at Tendean Pedestrian Bridge Site

    access_time18-07-2026 remove_red_eye1749 personFakhrizal Fakhri
  2. China-Based Training Equips PR Professionals and Journalists for Digital Media Transformation

    access_time19-07-2026 remove_red_eye1459 personFakhrizal Fakhri
  3. Rano Challenges Jakarta Provoke Organizers to Hold Exhibition Along Sudirman-Thamrin

    access_time18-07-2026 remove_red_eye1065 personBudhi Firmansyah Surapati
  4. Jakarta Supports Social Media Restrictions for Children

    access_time20-07-2026 remove_red_eye1035 personFakhrizal Fakhri
  5. Gas Stove Leak Sparks Fire, Gutting Five Rented Houses on Jalan Kayu Tinggi

    access_time17-07-2026 remove_red_eye972 personNurito