 Pembangunan MRT Jakarta Fase I Capai 97,06 Persen

Phase I MRT Development Has Reached 97.06 Percent

he three percent deficiency is still in progress at the interior and entrance

The progress on the construction of the phase I Jakarta Mass Rapid Transit (MRT) plying Lebak Bulus-HI Roundabout has reached 97.06 percent.

MRT Lebak Bulus-HI Roundabout Operational Socialization Intensified

"The three percent deficiency is still in progress at the interior and entrance," expressed William P. Sabandar, President Director of PT MRT Jakarta, Tuesday (10/30).

By so, he is optimistic that it will operate in accordance with the schedule in March 2019. Because until now the target of operations is still on time.

"In December 2018-February 2019, we will touch operation trial," he stated.

Linked News
Popular News indeks
  1. Jakarta Administration Steps Up Proactive Fire Prevention Efforts

    access_time09-10-2026 remove_red_eye537 personDessy Suciati
  2. MRT Jakarta Integrates Ticket Payments with JakLingko from October 12

    access_time10-10-2026 remove_red_eye537 personAldi Geri Lumban Tobing
  3. New Kelapa Gading-Pulogadung Road to Ease Traffic and Improve Access

    access_time10-10-2026 remove_red_eye529 personAldi Geri Lumban Tobing
  4. Kramat Pulo Fire Survivors Get Help Replacing School Documents

    access_time09-10-2026 remove_red_eye516 personFolmer
  5. Basic Supplies Distributed to Pinang Ranti Fire Survivors

    access_time09-10-2026 remove_red_eye506 personNurito