Pembangunan Skybridge Tanah Abang Capai 92 Persen

Tanah Abang Skybridge Now Entering Finishing Phase

Until November 5, Tanah Abang Skybridge construction in Central Jakarta has reached 92 percent.

Tanah Abang construction now reaches 92 percent or entering finishing phase

"Tanah Abang construction now reaches 92 percent or entering finishing phase where we will paint and install accessories to it," informed Yoory C. Pinontoan, PD. Pembangunan Sarana Jaya President Director, Tuesday (11/6).

He explained, Tanah Abang Skybridge will be integrated with Tanah Abang Market Block G and Block F which are managed by Perumda Pasar Jaya. Besides it will be also integrated with Transjakarta bus shelter and  Tanah Abang Station which is under management of PT. Kereta Api Indonesia (PT. KAI) and PT. Kereta Commuter Indonesia (KCI).

Citizens Request Road Access Near Skybridge

"We hope Tanah Abang Skybridge construction can create a new face for Tanah Abang primary center as the biggest trade center in Southeast Asia," he expressed.

Linked News
Popular News indeks
  1. Transjakarta Adjusts Routes Amid Demonstrations

    access_time28-10-2026 remove_red_eye600 personAldi Geri Lumban Tobing
  2. Central Jakarta Helps 879 Residents Retrieve Withheld Diplomas

    access_time30-10-2026 remove_red_eye557 personFolmer
  3. Jakarta to Host World Cities Culture Summit 2027

    access_time31-10-2026 remove_red_eye555 personBudhi Firmansyah Surapati
  4. Tourism Industry Workforce Capacity Continues to Be Improved

    access_time30-10-2026 remove_red_eye553 personAldi Geri Lumban Tobing
  5. Free Health Checks and TB Screening Held at RPTRA Tamplas Bambu

    access_time30-10-2026 remove_red_eye546 personNurito