Pembangunan Stasiun LRT Fase 1 Sudah 95 Persen

Stations Construction Hits 95 Percent for LRT Phase 1 Route

Construction progress on Light Rail Transit (LRT) Phase 1 (Velodrome-Kelapa Gading) station has reached 95 percent. There are six stations in this route which are targeted to complete by the end of this year.

Five stations will be completed this November

PT. LRT Jakarta Project Director, Iwan Takwin stated, LRT Phase 1 route is as long as 5.8 kilometers with six stations. Those are Pegangsaan Dua Station located in LRT Depot, Kelapa Gading (North Boulevard) Mall Station, South Boulevard Station, Pulomas Station, Equestrian Station, and Velodrome Station.

End of November, 6 LRT Stations will Be Completed

"Five stations will be completed this November. While the last station in depot will be completed in December," he informed, Monday (11/26).

He is targeting LRT transportation can be operated by the end of January 2019. Thus his side will test to operate this train before it is operated for public.

"Our target is to conduct trial run in two weeks from middle of January. After that it will ready to operate," he mentioned.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye384 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close