Pembangunan Stasiun LRT Fase 1 Sudah 95 Persen
.
photo Dadang Kusuma Wira Putra - Beritajakarta.id

Stations Construction Hits 95 Percent for LRT Phase 1 Route

Construction progress on Light Rail Transit (LRT) Phase 1 (Velodrome-Kelapa Gading) station has reached 95 percent. There are six stations in this route which are targeted to complete by the end of this year.

Five stations will be completed this November

PT. LRT Jakarta Project Director, Iwan Takwin stated, LRT Phase 1 route is as long as 5.8 kilometers with six stations. Those are Pegangsaan Dua Station located in LRT Depot, Kelapa Gading (North Boulevard) Mall Station, South Boulevard Station, Pulomas Station, Equestrian Station, and Velodrome Station.

End of November, 6 LRT Stations will Be Completed

"Five stations will be completed this November. While the last station in depot will be completed in December," he informed, Monday (11/26).

He is targeting LRT transportation can be operated by the end of January 2019. Thus his side will test to operate this train before it is operated for public.

"Our target is to conduct trial run in two weeks from middle of January. After that it will ready to operate," he mentioned.

Linked News
Popular News indeks
  1. Monas Prepares to Greet Visitors This Eid Holiday

    access_time30-03-2025 remove_red_eye723 personDessy Suciati
  2. Jakarta Vice Governor Rano Wishes a Happy Eid al-Fitr 1446 Hijri

    access_time31-03-2025 remove_red_eye616 personFolmer
  3. District Community Health Centers in East Jakarta Operate for 24 Hours

    access_time05-04-2025 remove_red_eye460 personNurito
  4. Backflow at Kampung Rambutan Terminal Increases as Mudik Return Flow Peaks

    access_time04-04-2025 remove_red_eye457 personNurito
  5. Kalideres Bus Terminal Adds 55 Night Transport Units

    access_time05-04-2025 remove_red_eye353 personTiyo Surya Sakti

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik