 Pembangunan Kolam Labuh Pulau Kelapa Capai 80 Persen

Docking Pool Construction Progress in Kelapa Island Reaches 80 Percent

Docking groove construction on the northern side of Kelapa Island Pier, North Seribu Islands, has reached 80 percent.

With this progress, we are optimistic to complete docking pool construction on the mid of December

Seribu Islands Transportation Sub-dept. Head, Robert Edward stated, docking groove construction consists of sheet pile installation, casting on pier and dike.

"With this progress, we are optimistic to complete docking pool construction on the mid of December," he conveyed, Wednesday (11/28).

Sebira Island's Docking Pool Targeted to Complete in December

He mentioned, Kelapa Island Docking Pool is constructed to realize resident's proposal on Musrenbang 2017 with total budget Rp 8.6 billion from APBD.

His side has prepared one stake tool and one excavator to ensure the construction can be completed on time. Besides, all building materials have been transported to the island.

"Currently, we just need to tidy it up, cast, and install con block," he added.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1090 personFolmer
  2. JIS-Ancol Integrated Infrastructure Officially Activated

    access_time23-06-2026 remove_red_eye575 personDessy Suciati
  3. Free Cake-Making Training Held at RPTRA Mustika Ratu

    access_time23-06-2026 remove_red_eye499 personNurito
  4. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye476 personAldi Geri Lumban Tobing
  5. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye474 personBudhi Firmansyah Surapati