 Pembangunan Kolam Labuh Pulau Kelapa Capai 80 Persen
.
photo Suparni - Beritajakarta.id

Docking Pool Construction Progress in Kelapa Island Reaches 80 Percent

Docking groove construction on the northern side of Kelapa Island Pier, North Seribu Islands, has reached 80 percent.

With this progress, we are optimistic to complete docking pool construction on the mid of December

Seribu Islands Transportation Sub-dept. Head, Robert Edward stated, docking groove construction consists of sheet pile installation, casting on pier and dike.

"With this progress, we are optimistic to complete docking pool construction on the mid of December," he conveyed, Wednesday (11/28).

Sebira Island's Docking Pool Targeted to Complete in December

He mentioned, Kelapa Island Docking Pool is constructed to realize resident's proposal on Musrenbang 2017 with total budget Rp 8.6 billion from APBD.

His side has prepared one stake tool and one excavator to ensure the construction can be completed on time. Besides, all building materials have been transported to the island.

"Currently, we just need to tidy it up, cast, and install con block," he added.

Linked News
Popular News indeks
  1. District Community Health Centers in East Jakarta Operate for 24 Hours

    access_time05-04-2025 remove_red_eye501 personNurito
  2. Backflow at Kampung Rambutan Terminal Increases as Mudik Return Flow Peaks

    access_time04-04-2025 remove_red_eye490 personNurito
  3. Kalideres Bus Terminal Adds 55 Night Transport Units

    access_time05-04-2025 remove_red_eye396 personTiyo Surya Sakti
  4. S. Jakarta Transportation Sub-agency Optimizes Services at Tourist Spots

    access_time03-04-2025 remove_red_eye358 personTiyo Surya Sakti
  5. Ship Surveillance in Bokor Island Waters Intensified for Eid Holiday

    access_time03-04-2025 remove_red_eye313 personAnita Karyati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik