 Pembangunan Kolam Labuh di Pulau Kelapa Ditarget Rampung Desember

Docking Groove Construction in Kelapa Island Targeted to Complete by December

Docking groove on the northern side of Kelapa Island Pier will be built and upgraded soon. It is targeted to complete by the end of December 2018.

Its budget is about Rp 8.6 billion and we plan to complete it in four months

Seribu Islands Transportation Sub-dept.'s Facility and Infrastructure Section Head, Suherman mentioned, his side starts to remeasure the site and ensure several works needed to be done in this project.

"Today we repeat the measurement for docking groove deepening. Later on, we will start the work," he said, Wednesdy (8/29).

Cilincing Floating Dock Construction Completed

He added, this construction is one of resident's requests in Musrenbang (development planning discussion).

"Its budget is about Rp 8.6 billion and we plan to complete it in four months," he informed.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye867 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye423 personFakhrizal Fakhri
  3. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye370 personDessy Suciati
  4. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye357 personDessy Suciati
  5. Several Microtrans Routes Diverted

    access_time31-01-2026 remove_red_eye353 personAldi Geri Lumban Tobing
close