Docking Pool Construction Progress in Kelapa Island Reaches 80 Percent

Docking groove construction on the northern side of Kelapa Island Pier, North Seribu Islands, has reached 80 percent.

With this progress, we are optimistic to complete docking pool construction on the mid of December

Seribu Islands Transportation Sub-dept. Head, Robert Edward stated, docking groove construction consists of sheet pile installation, casting on pier and dike.

"With this progress, we are optimistic to complete docking pool construction on the mid of December," he conveyed, Wednesday (11/28).

Sebira Island's Docking Pool Targeted to Complete in December

He mentioned, Kelapa Island Docking Pool is constructed to realize resident's proposal on Musrenbang 2017 with total budget Rp 8.6 billion from APBD.

His side has prepared one stake tool and one excavator to ensure the construction can be completed on time. Besides, all building materials have been transported to the island.

"Currently, we just need to tidy it up, cast, and install con block," he added.

Linked News
Popular News indeks
  1. Rano Reaffirms Jakarta's Vision of Becoming a City of Cinema

    access_time22-10-2026 remove_red_eye5473 personBudhi Firmansyah Surapati
  2. Jakarta Provincial Government Receives a Grant of Rp 9.6 Billion in KPK`s Seized Assets

    access_time20-10-2026 remove_red_eye4610 personDessy Suciati
  3. Drainage Channels Along Two Rawajati Roads Dredged

    access_time21-10-2026 remove_red_eye1815 personTiyo Surya Sakti
  4. Jakarta Pushed for Education Equity to Retain Top Student City Rank

    access_time19-10-2026 remove_red_eye1015 personFakhrizal Fakhri
  5. Jakarta Esports 2026: Celebrating Local Games, Music and More

    access_time19-10-2026 remove_red_eye1008 personAldi Geri Lumban Tobing