Docking Pool Construction Progress in Kelapa Island Reaches 80 Percent

Docking groove construction on the northern side of Kelapa Island Pier, North Seribu Islands, has reached 80 percent.

With this progress, we are optimistic to complete docking pool construction on the mid of December

Seribu Islands Transportation Sub-dept. Head, Robert Edward stated, docking groove construction consists of sheet pile installation, casting on pier and dike.

"With this progress, we are optimistic to complete docking pool construction on the mid of December," he conveyed, Wednesday (11/28).

Sebira Island's Docking Pool Targeted to Complete in December

He mentioned, Kelapa Island Docking Pool is constructed to realize resident's proposal on Musrenbang 2017 with total budget Rp 8.6 billion from APBD.

His side has prepared one stake tool and one excavator to ensure the construction can be completed on time. Besides, all building materials have been transported to the island.

"Currently, we just need to tidy it up, cast, and install con block," he added.

Linked News
Popular News indeks
  1. Transjakarta Brings Lunar New Year Festivities to Public Transport

    access_time16-02-2026 remove_red_eye977 personAldi Geri Lumban Tobing
  2. Free Transit Card Applications Skyrocket 143%, Passing 76k Mark

    access_time20-02-2026 remove_red_eye935 personAldi Geri Lumban Tobing
  3. Jakarta Govt-City Council Step Up Coordination to Address Key Urban Challenges

    access_time22-02-2026 remove_red_eye925 personFakhrizal Fakhri
  4. Public Works Agency Gets Transjakarta Corridor 13 Back in Tip-Top Shape

    access_time17-02-2026 remove_red_eye713 personAldi Geri Lumban Tobing
  5. Chinese New Year Holiday, Ancol Flocked by Visitors

    access_time16-02-2026 remove_red_eye609 personAnita Karyati