Pier Construction on The Eastern Side of Pramuka Island Reaches 75 Percent

Pier construction progress located in the eastern side of Pramuka Island, Panggang Island, North Seribu Islands now reaches 75 percent.

Current progress of pier construction is already 75 percent and now it is entering finishing stage

Seribu Islands Transportation Sub-dept.'s Facilities and Infrastructure Section Head, Suherman stated, this construction are consisting of stakes installation, sheet pile installation, groove deepening, and elevating dike walls.

"Current progress of pier construction is already 75 percent and now it is entering finishing stage," he mentioned, Friday (11/30).

Docking Pool Construction Progress in Kelapa Island Reaches 80 Percent

He explained, the rest of construction work is only finishing dike and pier walls. This pier will be used to dock fishermen boats and also boats to transport tourists.

This construction is done to follow up one of resident's proposals in Musrenbang 2017 with total budget Rp 9.7 billion.

"We are targeting this pier to finish in mid December," he conveyed.

Linked News
Popular News indeks
  1. Attending Betawi Eid 2026, Pram Encourages Strengthening Cultural Values

    access_time11-04-2026 remove_red_eye1080 personFolmer
  2. Low Emission Zones: Jakarta’s Concrete Step to Curb Air Pollution

    access_time13-04-2026 remove_red_eye1013 personAldi Geri Lumban Tobing
  3. Jakpro Promotes Integration Between JIS and KRL Station

    access_time10-04-2026 remove_red_eye857 personAldi Geri Lumban Tobing
  4. Cilandak Health Center Maintains Optimal Services

    access_time10-04-2026 remove_red_eye823 personTiyo Surya Sakti
  5. Palmeriam Market Adopts QRIS Digital Payment System

    access_time08-04-2026 remove_red_eye721 personNurito