You don't have javascript enabled. Good luck with that.
Pencarian
 Pembangunan IPAL di Pulau Harapan Capai 40 Persen

Harapan Island IPAL Construction Reaches 40 Percent

Process of Wastewater Treatment Plant (IPAL) construction at RT 01/01 Harapan Island Urban Island, North Thousand Islands has reached 40 percent.

IPAL construction that is built with budget Rp 12.9 billion is targeted to complete on December 15

Thousand Islands Water Resources (SDA) Sub-department Head, Mustajab conveyed, this IPAL can accommodate domestic wastewater from two RWs in Harapan Island with total channel capacity to reach 500 houses.

"IPAL construction that is built with budget Rp 12.9 billion is targeted to complete on December 15," he stated, Thursday (10/31).

Tanjung Duren Locals Collaborate with Abdi Rakyat to Develop IPAL

Harapan Island Urban Village Secretary, Irfan Damanhuri explained, IPAL will be used to manage domestic wastewater in the region thus it could reduce groundwater and sea water pollution.

"If it is managed properly, wastewater that flows into the sea is already clean thus it doesn't pollute the environment," he explained.

Linked News
Popular News indeks
  1. Cilandak Drainage Upgraded to Mitigate Flooding

    access_time27-01-2026 remove_red_eye869 personTiyo Surya Sakti
  2. TransJabodetabek Expansion, a Strategic Step to Increase Public Transportation Use

    access_time26-01-2026 remove_red_eye428 personFakhrizal Fakhri
  3. South Jakarta Tackles 38 Dengue Cases to Prevent Outbreak

    access_time02-02-2026 remove_red_eye417 personTiyo Surya Sakti
  4. Jakarta Prepares OMC and 200 Excavators to Prevent Flood

    access_time26-01-2026 remove_red_eye371 personDessy Suciati
  5. Jakarta Showers to Make Way for Partly Cloudy Skies

    access_time30-01-2026 remove_red_eye359 personDessy Suciati
close