Pembangunan JIS Capai 26,4 Persen

JIS Construction Progress Has Touched 26 Percent

PT Jakarta Propertindo (Jakpro) says the construction progress of the Jakarta International Stadium (JIS) has reached 26.4 percent.

JIS will have 235,127 square meters with a capacity of 82,000 audiences

"Currently we are focusing on the construction of two training fields as wide as 15,696 square meters and planting the Italian 'zoysia matrella' hybrid grass," stated Corporate Communication and Commercial for JIS Project, Arnold Kindangan, Wednesday (8/26).

His party was also casting zone 16 on the north side of JIS. It was a continuation of the ground floor casting, which was completed last week.

Foundation Cover Casting for JIS Main Pile Has Been Completed

"JIS will have 235,127 square meters with a capacity of 82,000 audiences," he said.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1445 personFolmer
  2. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye974 personFolmer
  3. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye880 personAldi Geri Lumban Tobing
  4. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye776 personAldi Geri Lumban Tobing
  5. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye687 personAldi Geri Lumban Tobing