Pengerjaan MRT Fase 2 Segmen CP-201, Lalin Jalan MH Thamrin Direkayasa
.
photo istimewa - Beritajakarta.id

Dishub Applies Traffic Engineering on Jalan MH Thamrin Due to MRT Phase 2 CP-201 Section Construction

Jakarta Transportation Agency (Dishub) applied traffic engineering on Jalan MH. Thamrin due to the commencement of Mass Rapid Transit (MRT) Phase 2 construction project for CP-201 Bundaran Hotel Indonesia (HI) - Simpang Harmoni section.

During the construction, there will be reduction of one regular lane on the east side of Jalan MH. Thamrin along the construction area

Jakarta Dishub Head, Syafrin Liputo conveyed, test pit work on the median of Jalan MH. Thamrin carried out from September 22 to October 30,2020. During the construction, Transjakarta route applied mix traffic with regular route along the construction area.

At the same time, road widening and sidewalk demolition also carried out in front of Sinar Mas Building from September 22 to October 16, 2020.

Japanese Ambassador Conveys His Appreciation for MRT Phase 2 Project

"During the construction, there will be reduction of one regular lane on the east side of Jalan MH. Thamrin along the construction area," he explained, Tuesday (9/22).

The next stage is widening construction site on the median of Jalan MH. Thamrin to the south from October 17 to November 19, 2020.

According to him, sidewalk that has been demolished can be used as traffic lane and Transjakarta bus will carry out mix traffic with regular lane along construction area.

Furthermore, construction will be also carried out on the west side of Jalan MH. Thamrin (regular lane) from November 20 to December 23, 2020 thus traffic diversion wil be divided into west and east sides along the construction area.

For archaelogical work at Intersection of Jalan MH. Thamrin -  Jalan Kebon Sirih on the south side of Tugu Jam, will be held from September 22 to October 15, 2002, thus there will be reduction in lane along the construction area.

In addition, other test pit work is also carried out, namely,

- Test pit TP-19A on Jalan Museum (middle side) on September 22 - October 4, 2020.

- Test pit TP-18 on Jalan Museum (east side) on September 22 - October 19, 2020;

- TP-25 on Jalan Kebon Sirih (east side, in front of Bank Bangkok) on October 2 - 18, 2020;

- TP-10 on Jalan Kebon Sirih (west side) on the median of the road on October 9 - 25, 2020;

- TP-23 on Jalan Kebon Sirih (east side, in front of Wisma Mandiri) on October 24 - November 9, 2020

"There is reduction in lane width along the construction area," he stated.

Linked News
Popular News indeks
  1. Pramono Ensures KJP will Continue to Be Distributed

    access_time26-06-2025 remove_red_eye304 personDessy Suciati
  2. Most Residents Satisfied with Pramono-Rano's Performance

    access_time25-06-2025 remove_red_eye303 personDessy Suciati
  3. Governor Pramono: Jakarta E-Prix 2025 in Ancol is Amazing!

    access_time21-06-2025 remove_red_eye267 personDessy Suciati
  4. Here are Parking Spaces around Lapangan Banteng for Jakarta's Anniversary

    access_time21-06-2025 remove_red_eye262 personAldi Geri Lumban Tobing
  5. No Car Free Day on June 29 to Support Jakarta International Marathon 2025

    access_time24-06-2025 remove_red_eye238 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik