Pembangunan Embung Wirajasa Capai 30 Persen
.
photo Nurito - Beritajakarta.id

Construction of Wirajasa Retention Basin Reaches 30 Percent

Construction of Wirajasa Retention Basin (embung) on Jl. Wirajasa, RW 06 Cipinang Melayu, Makasar, East Jakarta has reached 30 percent.

Our target is to finish the construction by the end of December

East Jakarta Water Resources (SDA) Sub-agency Head, Santo mentioned, this construction which carried out on 7,128 square meters land was needed to overcome flooding that often occur at RW 06, 07, and 08 Cipinang Melayu.

"We start the construction about two weeks ago and now it reaches 30 percent. Our target is to finish the construction by the end of December," he explained, Wednesday (9/23).

SDA to Realize Zero Inudation in Jakarta

His side used 3 units of excavator to dredge about 3 meters depth to build the retention basin.

"We hope it can reduce inundation and flooding in the region," he said.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye524 personBudhi Firmansyah Surapati
  2. Rano Requests PBSI to Hold Governor's Cup Championship

    access_time31-05-2025 remove_red_eye414 personBudhi Firmansyah Surapati
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye390 personDessy Suciati
  4. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye381 personAldi Geri Lumban Tobing
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye271 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik