Construction of Wirajasa Retention Basin Reaches 30 Percent
access_time September 23 2020 07:09 PM remove_red_eye 970
Reported by Nurito | Translated by Maria Inggita
Reported by Nurito | Translated by Maria Inggita
Construction of Wirajasa Retention Basin (embung) on Jl. Wirajasa, RW 06 Cipinang Melayu, Makasar, East Jakarta has reached 30 percent.
Our target is to finish the construction by the end of December
East Jakarta Water Resources (SDA) Sub-agency Head, Santo mentioned, this construction which carried out on 7,128 square meters land was needed to overcome flooding that often occur at RW 06, 07, and 08 Cipinang Melayu.
"We start the construction about two weeks ago and now it reaches 30 percent. Our target is to finish the construction by the end of December," he explained, Wednesday (9/23).
SDA to Realize Zero Inudation in JakartaHis side used 3 units of excavator to dredge about 3 meters depth to build the retention basin.
"We hope it can reduce inundation and flooding in the region," he said.