JIS Project Work Has Reached 28.64 Percent

The Jakarta International Stadium (JIS) construction, Tanjung Priok, North Jakarta is still undergoing. It has touched 28.64 percent and the deviation reaches -2.52 percent.

We're also working on the training field area and erecting the west ramp of the BMW park

Arnold Kindangen, Corporate Communication & Commercial for JIS Project said, from the value of realization progress based on the calculation of the Operational Cooperation (KSO), the project plan was to reach 31.16 percent.

"Deviation is -2.52 percent due to constraints in the material import process related to the import restriction policy from the government to empower local products. The project requires imported steel materials from China for the construction of a roof that can be opened and closed as much as 5,000 tons, but now only 200 tons," he expressed, Friday (10/2).

PAM Jaya to Supply JIS's Clean Water Next Year

He stated, for shortages of steel roof construction materials were still in process and scheduled in this week was already on the way. As for the synthetic grass used was Limonta Mixto from Italy, which was currently in Tanjung Priok Port.

To speed up the project work, his party would optimize works that could be advanced such as working on training fields. While the construction that was currently underway included the 1st, 2nd, 3rd, 4th, 5th, 6th and 7th floor construction.

"We're also working on the training field area and erecting the west ramp of the BMW park," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1709 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1481 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1335 personFolmer
  4. Pramono will Take Firm Action Against Individuals Involved in Extortion

    access_time13-07-2026 remove_red_eye1120 personDessy Suciati
  5. The Pegangsaan Dua-Manggarai LRT Project Reaches 95 Percent Completion

    access_time14-07-2026 remove_red_eye815 personDessy Suciati