Pembuatan Embung di Semanan Sudah Mencapai 70 Persen
.
photo Rudi Hermawan - Beritajakarta.id

Rusun Pesakih Retention Basin Construction Reaches 70 Percent

Progress of Rusun Pesakih Retention Basin construction in Jalan Kampung Duri, Semanan, Kalideres, Wes Jakarta has reached 70 percent.

Its progress has reached 70 percent. We estimate it to finish by the end of this month

West Jakarta Water Resources (SDA) Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, Wawan mentioned this reteition basin is built as wide as 2,598 square meters and depth of 4.5 meters above 6,442 square meters land owned by Jakarta Park and Urban Forest (Disparhut) Agency.

"Its progress has reached 70 percent. We estimate it to finish by the end of this month," he conveyed, Wednesday (11/11).

Process of Tegal Alur Retention Basin Construction Reaches 70 Percent

For its construction, his side deployed four heavy equipment units, such as standard excavator, long excavator, small amphibians, and long arm excavator.

In the future, this reservoir will be used to store water and drain the water to Mookevart River.

"We built this retention basin to overcome inundation and flood in the region," he closed.

Linked News
Popular News indeks
  1. Rano Inspects Location and Delivers Aid to Fire Victims in Bukit Duri

    access_time20-07-2025 remove_red_eye577 personNurito
  2. Assistance Continues to Be Provided to Bukit Duri Fire Victims

    access_time20-07-2025 remove_red_eye412 personNurito
  3. C. Jakarta TP PKK Grows 2,470 Chili and Tomato Seedlings

    access_time18-07-2025 remove_red_eye386 personFolmer
  4. Rano Ensures Swift Action in Bukit Duri Fire Handling

    access_time19-07-2025 remove_red_eye382 personFakhrizal Fakhri
  5. Munjirin Leads Simultaneous Planting at RPTRA Rawa Jaya

    access_time18-07-2025 remove_red_eye379 personNurito

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik