JIS Construction Progress Reaches 35.8 Percent
access_time November 18 2020 08:12 PM remove_red_eye 1167
Reported by Wuri Setyaningsih | Translated by Maria Inggita
Reported by Wuri Setyaningsih | Translated by Maria Inggita
PT. Jakarta Propertindo (Jakpro) continues the the construction of Jakarta International Stadium (JIS) in Tanjung Priok, North Jakarta. Entering 63th week, its progress has reached 35.8 percent where the construction has entered the main stadium concourse.
We are also working on tribune beams installation and tribune precast
Corporate Communication & Commercial for JIS Project, Arnold Kindangen conveyed, his side has started the construction of main stadium concourse with west ramp erection and beam casting on the east ramp.
"We are also working on tribune beams installation and tribune precast. MEP work for plumbing and ducting, as well as final phase for training field 1 and tribune has been started," he mentioned, Wednesday (11/18).
Process of JIS Construction Reaches 34.13 PercentFor information, JIS will be built on 235,127 square meters area with capacity of 82 thousand people. This stadium will also be equipped with various modern and international standard facilities that will be the pride of Jakarta residents.