Minggu ke 63 Progres Konstruksi JIS telah Mencapai 35,8
.
photo Wuri Setyaningsih - Beritajakarta.id

JIS Construction Progress Reaches 35.8 Percent

PT. Jakarta Propertindo (Jakpro) continues the  the construction of Jakarta International Stadium (JIS) in Tanjung Priok, North Jakarta. Entering 63th week, its progress has reached 35.8 percent where the construction has entered the main stadium concourse.

We are also working on tribune beams installation and tribune precast

Corporate Communication & Commercial for JIS Project, Arnold Kindangen conveyed, his side has started the construction of main stadium concourse with west ramp erection and beam casting on the east ramp.

"We are also working on tribune beams installation and tribune precast. MEP work for plumbing and ducting, as well as final phase for training field 1 and tribune has been started," he mentioned, Wednesday (11/18).

Process of JIS Construction Reaches 34.13 Percent

For information, JIS will be built on 235,127 square meters area with capacity of 82 thousand people. This stadium will also be equipped with various modern and international standard facilities that will be the pride of Jakarta residents.

Linked News
Popular News indeks
  1. Waste Sorting Education Given for 500 Students of SDN 07

    access_time26-04-2024 remove_red_eye746 personAnita Karyati
  2. 37.25 Ton of Campaign Prop Waste in West Jakarta Recycled

    access_time26-04-2024 remove_red_eye508 personTP Moan Simanjuntak
  3. LRT Phase 1B Construction Remains Positive

    access_time27-04-2024 remove_red_eye435 personAldi Geri Lumban Tobing
  4. East Jakarta Sudinhub Replaces 38 Broken Convex Traffic Mirrors

    access_time26-04-2024 remove_red_eye383 personNurito
  5. 81 Pets in West Jakarta Get Anti Rabies Vaccine

    access_time26-04-2024 remove_red_eye379 personTP Moan Simanjuntak