Minggu ke 63 Progres Konstruksi JIS telah Mencapai 35,8

JIS Construction Progress Reaches 35.8 Percent

PT. Jakarta Propertindo (Jakpro) continues the  the construction of Jakarta International Stadium (JIS) in Tanjung Priok, North Jakarta. Entering 63th week, its progress has reached 35.8 percent where the construction has entered the main stadium concourse.

We are also working on tribune beams installation and tribune precast

Corporate Communication & Commercial for JIS Project, Arnold Kindangen conveyed, his side has started the construction of main stadium concourse with west ramp erection and beam casting on the east ramp.

"We are also working on tribune beams installation and tribune precast. MEP work for plumbing and ducting, as well as final phase for training field 1 and tribune has been started," he mentioned, Wednesday (11/18).

Process of JIS Construction Reaches 34.13 Percent

For information, JIS will be built on 235,127 square meters area with capacity of 82 thousand people. This stadium will also be equipped with various modern and international standard facilities that will be the pride of Jakarta residents.

Linked News
Popular News indeks
  1. Pram-Rano Attend Bung Karno Festival at Proklamasi Park

    access_time20-06-2026 remove_red_eye1079 personFolmer
  2. Metropolitan City Rally 2026 to Be Held at City Hall

    access_time19-06-2026 remove_red_eye463 personAldi Geri Lumban Tobing
  3. Rano Officially Opens Discover Betawi Art and Culture 2026

    access_time19-06-2026 remove_red_eye462 personBudhi Firmansyah Surapati
  4. Setu Babakan Presents Arts and Culture Extravaganza to Mark Jakarta Anniversary

    access_time20-06-2026 remove_red_eye431 personNurito
  5. Jakarta Light Festival Dazzles Visitors at Kota Tua

    access_time22-06-2026 remove_red_eye400 personBudhi Firmansyah Surapati