 Kolam Olakan di Jelambar Sudah 60 Persen
....
photo Rudi Hermawan - Beritajakarta.id

Stilling Basin Construction in Jelambar Reaches 60 Percent

The progress of stilling basin construction work on Jalan Satria Raya, Jelambar, Grogol Petamburan which carried out by West Jakarta Water Resources (SDA) Sub-agency has reached 60 percent.

We build this stilling basin to minimize inundation in Jelambar Urban Village

Grogol Petamburan SDA Unit Head, Agus conveyed, this stilling basin with length 5.5 meters, width 1.5 meters, and height 3 meters is expected to accommodate water with volume up to 25 qubic meters.

"We build this stilling basin to minimize inundation in Jelambar Urban Village," he explained, Friday (11/20).

SDA Accelerates Stilling Basins Construction in Kelapa Gading

For the construction, his side deployed 25 personnel from Grogol Petamburan SDA Unit.

Anticipating inundation and flood in the area, his side not only built stilling basin, but also prepared water pump that can drain the water to Grogol River.

"We estimate to finish building this stilling basin by the end of November," he stated.

Linked News
Popular News indeks
  1. Rano: Pancasila is the Big House for Indonesia's Diversity

    access_time02-06-2025 remove_red_eye526 personBudhi Firmansyah Surapati
  2. Friendly Countries' Ambassadors Participate in Famtrip to Seribu Islands

    access_time05-06-2025 remove_red_eye398 personAldi Geri Lumban Tobing
  3. Transjabodetabek Bogor–Blok M Route and Corridor 13 Extension Begin Operations

    access_time05-06-2025 remove_red_eye396 personDessy Suciati
  4. S. Jakarta Mayor: Idul Adha is a Moment to Enhance Compassion Among One Another

    access_time06-06-2025 remove_red_eye274 personTiyo Surya Sakti
  5. No Odd-Even Restrictions in Jakarta on June 6-9, 2025

    access_time03-06-2025 remove_red_eye271 personAldi Geri Lumban Tobing

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik