Gerebek Lumpur di Kali Mampang Capai 70 Persen

Mud Dredging Work in Mampang River Has Reached 70 Percent

The mud dredging process in Mampang River as long as one kilometer starting from Pasar Jagal Warung Buncit until Jalan Pondok Jaya, Mampang Prapatan, South Jakarta has reached 70 percent.

It only leaves more or less about 200 meters to Pondok Jaya

"It only leaves more or less about 200 meters to Pondok Jaya," expressed Jakarta Water Resources (SDA) Agency Head, Juaini Yusuf, Friday (11/20).

He explained two amphibious excavators had been operated to dredge up mud from the river. Sedimentation and river narrowing had made the area around Mampang River often flooded when the water flow was high.

Central Jakarta Continues to Optimize Flood Mitigation

That was why it was done to accommodate water in large quantities when rain poured. "The river has six meter width thus we operate two excavators. So we dredge up the mud up to five meters from the surface," he stated.

Linked News
Popular News indeks
  1. Jakarta Claims Rp 2.27 T in Public Assets from Developer Obligations

    access_time06-08-2026 remove_red_eye701 personDessy Suciati
  2. New LapakMain Corner Creative Hub Inaugurated at Tunas Muda RPTRA, Kramat Pela

    access_time05-08-2026 remove_red_eye590 personTiyo Surya Sakti
  3. Jakarta Remains Indonesia's Top Investment Destination

    access_time07-08-2026 remove_red_eye476 personAldi Geri Lumban Tobing
  4. Abdul Muis Building Fire Response Nears Completion, No Fatalities Reported

    access_time08-08-2026 remove_red_eye473 personAldi Geri Lumban Tobing
  5. Thousand Islands Conducts Vehicle Emission Tests on Three Islands

    access_time07-08-2026 remove_red_eye473 personAnita Karyati