Next Week, Stilling Basin Construction at SDN 05 Srengseng is Targeted to Finish

Stilling basin construction at SDN 05, Jalan Srengseng Raya, Srengseng, Kembangan, West Jakarta was targeted to finish next week.

This work is targeted to finish next week

Kembangan Sub-district Water Resources (SDA) Unit Head, Mulyadi mentioned, this work had been carried out since October 2020. This stilling basin was planned to have length and width of 4 meters with height 2.3 meters.

"This work is targeted to finish next week," he said, Monday (11/30).

Stilling Basin Construction on Jl. Kedoya Raya Targeted to Finish in December

For the construction, his side deployed 20 personnel which divided into 2 teams.

"We build this stilling basin to overcome inundation on Jalan Srengseng Raya," he conveyed.

Linked News
Popular News indeks
  1. Central Jakarta Administration Acts Swiftly to Handle Kebon Kosong Fire

    access_time02-06-2026 remove_red_eye1460 personFolmer
  2. Public Urged to Use Public Transit for GBK Events to Avoid Heavy Traffic

    access_time05-06-2026 remove_red_eye1255 personAldi Geri Lumban Tobing
  3. Traffic Measures Prepared to Ease Congestion Around GBK This Weekend

    access_time04-06-2026 remove_red_eye1147 personAldi Geri Lumban Tobing
  4. Central Jakarta Government Responds Quickly to Fire Victims in Tanah Tinggi

    access_time04-06-2026 remove_red_eye1002 personFolmer
  5. Jakarta Waives Motor Vehicle Tax Fines and Title Transfer Fees

    access_time01-06-2026 remove_red_eye895 personAldi Geri Lumban Tobing