You don't have javascript enabled. Good luck with that.
Pencarian
Perbaikan Turap Kali Baru di Rawa Bunga Capai 85 Persen
.
photo Nurito - Beritajakarta.id

Baru River Retaining Wall Repair in Jatinegara Touches 85 Percent

Baru River retaining wall repair work on Jalan Kemuning Mede, RT 05/01 Rawa Bunga, Jatinegara, East Jakarta has touched 85 percent.

For now, we have repaired it along 35 meters or its pr ogress has reached 85 percent

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Section Head, Puryanto mentioned, collapsed retaining walls repair has been carried out since two weeks ago.

"For now, we have repaired it along 35 meters or its progress has reached 85 percent," he added, Tuesday (12/1).

Channel's Retaining Wall Repair on Jl. Pramuka Touches 30 Percent

His side deployed 15 SDA personnel to repair the collapsed retaining wall.

"It is estimated to finish in mid of December," he conveyed.

Linked News
Popular News indeks
  1. Five Transjabodetabek Routes will Be Added to Tackle Traffic Congestion

    access_time09-05-2025 remove_red_eye668 personDessy Suciati
  2. Tanah Abang SDA Taskforce Normalizes Channels in Two Locations

    access_time12-05-2025 remove_red_eye458 personFolmer
  3. Munjirin Optimizes Physical and Non-Physical Development in East Jakarta

    access_time08-05-2025 remove_red_eye377 personNurito
  4. Community Work Held to Clean Environment in Petamburan

    access_time11-05-2025 remove_red_eye354 personFolmer
  5. Baduy Tribe Meets Pramono-Rano, Leaves Message of Protecting Nature

    access_time09-05-2025 remove_red_eye294 personDessy Suciati

Hitung Mundur 22 Juni 2027

00
Hari
00
Jam
00
Menit
00
Detik