The Thousand Islands Water Resources (SDA) Sub-agency has completed repair of the breakwater to absorb the energy of the waves that hit it on the north side of Untung Jawa Island, Untung Island Jawa Urban Village, South Thousand Islands Sub-district.

The barrier stretches for 422 meters covering the areas of RT 01/03, RT 02/02 and RT 03/03. This repair project includes, reinstalling the cube, installing wire gabions and casting the top of the barrier.

Eleven Breakwater Embankments on Residential Islands Installed

Thousand Islands SDA Sub-agency Head Abdul Rouf said, the barrier collapsed after being hit by waves last June.

"Then we immediately repaired it in stage by sending 24 personnel and it was finished last month," he told.

By so, the settlements on Untung Jawa Island would be safe from waves that might trigger inundation or flooding.

"Certainly this can reduce the risk of abrasion and tidal wave," he stated.

Linked News
Popular News indeks
  1. Jakarta Taps MSMEs and Creative Economy to Secure Global Top 50 Spot

    access_time11-07-2026 remove_red_eye1581 personAldi Geri Lumban Tobing
  2. Ciliwung River Normalization Accelerated, Pramono Ensures Land Acquisition Without Intermediaries

    access_time10-07-2026 remove_red_eye1438 personDessy Suciati
  3. Blocked Drain on Jalan Palmerah Utara is Being Repaired

    access_time10-07-2026 remove_red_eye1302 personFolmer
  4. Jalan Kebon Kelapa I Repaved

    access_time07-07-2026 remove_red_eye1095 personNurito
  5. Pramono Inaugurates Mayapada Hospital to Improve Healthcare Services

    access_time09-07-2026 remove_red_eye966 personDessy Suciati