Roofs Painting Progress in Lenteng Agung Reaches 85 Percent
access_time January 04 2021 07:10 PM remove_red_eye 864
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
Reported by TP Moan Simanjuntak | Translated by Maria Inggita
The progress of painting residents houses' roofs near Lenteng Agung Flyover, South Jakarta has reached about 85 percent.
Saat ini sudah 192 atap rumah warga yang sudah selesai dicat,
Lenteng Agung Urban Village Head, Bayu Pasca Sungkono conveyed, 192 houses' roofs have been painted from total 218 houses in RW 01, 02, 03, and 05.
"So far, 192 houses' roofs have been painted," he asserted, Monday (1/4).
Lenteng Agung Flyover Beautification Program Touches 25 PercentEvery day, his side deployed 24 PPSU personnel with assistance from mural community members from Jakarta Arts Council (DKJ) to paint the roofs. If the weather is clear, the work is expected to complete on January 11, 2021.
"It could be finished on January 11 if the weather is clear," he mentioned.