Plh Walikota Jakpus Optimis Pengerukan Kali Sentiong Atasi Genangan
.
photo Reza Hapiz - Beritajakarta.id

Mud Dredging Process in Sentiong River has Reached 95 Percent

The settlements along the river are no longer flooded when it rains

The mud dredging process in Sentiong River, Johar Baru, Central Jakarta has touched 95 percent.

Central Jakarta Acting Mayor Irwandi said, mud dredging had been ongoing since October 2019 and is targeted to be complete by the end of January 2021.

Progress of JGC Side C Reservoir Dredging Work Touches 50 Percent

"The settlements along the river are no longer flooded when it rains," he told, Friday (1/15).

He told, the water downstream is already flowing fast as the river had been dredged. Thus there are no more blockages that cause water to overflow.

"Despite the rainfall is not high, we believe it is able to overcome flooding that often occurs in local residents," he stated.

Linked News
Popular News indeks
  1. Survivors of Collapsed Houses in Malaka Jaya Receive Social Assistance

    access_time30-01-2025 remove_red_eye2206 personNurito
  2. Logistics Aid for Jakarta Flood Victims Keeps Being Distributed

    access_time30-01-2025 remove_red_eye982 personAldi Geri Lumban Tobing
  3. City Council Chairman Supports City Government Optimizing Assistance for Rorotan Farmers

    access_time30-01-2025 remove_red_eye674 personDessy Suciati
  4. N. Jakarta Vice Mayor Distributes Assistance to Flood Survivors in Sukapura

    access_time30-01-2025 remove_red_eye480 personAnita Karyati
  5. Rain Brings Excitement to Rawa Belong Milkfish Festival 2025

    access_time28-01-2025 remove_red_eye449 personFolmer