Damaged Wave Barriers on Untung Jawa Island Being Repaired
access_time January 20 2021 05:27 PM remove_red_eye 943
Reported by Suparni | Translated by Nugroho Adibrata
Reported by Suparni | Translated by Nugroho Adibrata
It has been ongoing since January 18 and is targeted to be complete in a week
The Thousand Islands Water Resources (SDA) Sub-agency has started repairing the damaged wave barriers in Untung Jawa Island Urban Village, South Thousand Islands Sub-district.
Thousand Islands SDA Sub-agency Head Abdul Rouf said, the damage was caused by high waves for several weeks.
Wave Barrier Repair on Untung Jawa Island Completed"Two are being repaired so far. Each has 80 meters long behind the SWRO building and 70 meters long on the south side of the pier," he expressed, Wednesday (1/20).
To conduct the repair, he explained, as many as 20 personnel had been alerted to the location.